Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget. ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-generated project schedule. iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ interviews, ♦ data collection ♦ analysis, ♦ report preparation, ♦ planning, ♦ Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables. iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-consultants, and DISTRICT staff. v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project. vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project. vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project. viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan. ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution. x - Base Drawings and Site Survey Information
Appears in 7 contracts
Samples: Agreement for Architectural Services, Architectural Services Agreement, Agreement for Architectural Services
Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget.
ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-computer- generated project schedule.
iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ interviews, ♦ data collection ♦ analysis, ♦ report preparation, ♦ planning, ♦ Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables.
iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-sub- consultants, and DISTRICT staff.
v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project.the
vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project.
vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution.
x - Base Drawings and Site Survey Information
Appears in 5 contracts
Samples: Agreement for Architectural Services, Agreement for Architectural Services, Architectural Services Agreement
Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget.
ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-computer- generated project schedule.
iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ interviews, ♦ data collection ♦ analysis, ♦ report preparation, ♦ planning, ♦ Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables.
iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-sub- consultants, and DISTRICT staff.
v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project.the
vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project.
vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution.
x - Base Drawings and Site Survey Information
Appears in 3 contracts
Samples: Architectural Services Agreement, Architectural Services Agreement, Agreement for Architectural Services
Project Initiation. i - Upon final execution of the Agreement with the DISTRICTDistrict, the ARCHITECT Bridging Architect shall: ♦ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget.:
ii - a. Within the first week following execution of the Agreement, meet with the DISTRICT District and its representatives to prepare a detailed task analysis an initial scope of work and work plan for documentation in a computer-generated project scheduleschedule all in compliance with the schedule indicated in Exhibit C of this Agreement.
iii - b. This task analysis scope of work and work plan will identify specific tasks including, but not limited to: ♦ interviews, ♦ data collection ♦ collection, analysis, ♦ report preparation, ♦ planning, ♦ Architectural architectural programming, concepts and concepts, schematic design, bridging design document preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT District and by all regulatory agencies and additional definition of deliverables.
iv - c. Review the developed work plan with the District and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications.
d. Participate and take meeting minutes in a general Project kick-off meeting to include the ARCHITECTBridging Design Team, appropriate sub-consultantssubconsultant(s), Program Manager and DISTRICT District staff/stakeholders.
v - 1) The project Project kick-off meeting will introduce key team members from the DISTRICT District or its authorized representative(s), Maintenance and Operations and the ARCHITECT Bridging Architect’s Team to each other, defining roles and responsibilities relative to the Project.
vi - 2) Identify and review pertinent information and/or documentation necessary from the DISTRICT District for the Bridging Architect’s completion of the ProjectServices.
vii - 3) Review and explain the overall project Project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - 4) Review and explain the task analysis scope of work and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - 5) Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative District's Project Manager and comment prior to distribution.
x - Base Drawings e. Review and Site Survey Informationimplement as appropriate the latest District Design and Material Standards. District standards may include, without limitation, standardized materials/equipment, design elements, technology interfaces, and project scheduling methodology.
Appears in 2 contracts
Samples: Bridging Architectural/Engineering Services Agreement, Bridging Architectural/Engineering Services Agreement
Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ ◆ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget.
ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-generated project schedule.
iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ ◆ interviews, ♦ ◆ data collection ♦ ◆ analysis, ♦ ◆ report preparation, ♦ ◆ planning, ♦ ◆ Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables.
iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-consultants, and DISTRICT staff.
v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project.
vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project.
vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution.
x - Base Drawings and Site Survey Information
Appears in 2 contracts
Samples: Agreement for Architectural Services, Agreement for Architectural Services
Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget.
ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-computer- generated project schedule.
iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ interviews, ♦ data collection ♦ analysis, ♦ report preparation, ♦ planning, ♦ Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables. Provision of two (2) three dimensional renderings of conceptual perspective/rendering by August 17, 2012.
iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-sub- consultants, and DISTRICT staff.
v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project.the
vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project.
vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution.
x - Base Drawings and Site Survey Information
Appears in 1 contract
Samples: Professional Services
Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget.
ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-generated project schedule.
iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ interviews, ♦ data collection ♦ analysis, ♦ report preparation, ♦ planning, ♦ Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables.
iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-consultants, and DISTRICT staff.
v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project.
vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project.
vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution.
x - Base Drawings and Site Survey Information
Appears in 1 contract
Samples: Architectural Services Agreement
Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ ◆ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget. ◆ Review District CAD standards to familiarize and ensure all deliverables are provided in accordance with standards.
ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-generated project schedule.
iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ ◆ interviews, ♦ ◆ data collection ♦ ◆ analysis, ♦ ◆ report preparation, ♦ ◆ planning, ♦ ◆ Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables.
iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-consultants, and DISTRICT staff.
v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project.
vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project.
vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution.
x - Base Drawings and Site Survey Information
Appears in 1 contract
Samples: Agreement for Architectural Services
Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget.
ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-computer- generated project schedule.
iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ interviews, ♦ data collection ♦ analysis, ♦ report preparation, ♦ planning, ♦ development of the District Standards as it pertains to intrusion security systems development of an RFP for vendor selection in order to base the overall equipment on a single vendor/manufacturer Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables.
iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-sub- consultants, and DISTRICT staff.
v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project.the
vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project.
vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution.
x - Base Drawings and Site Survey Information
Appears in 1 contract
Samples: Professional Services
Project Initiation. i - Upon final execution of the Agreement with the DISTRICT, the ARCHITECT shall: ♦ ◆ Review the Program Management Plan (PMP) with the DISTRICT and its representatives to familiarize them with the proposed tasks and schedule and develop necessary modifications. The PMP defines the Program Master Schedule and Budgets and each Project scope and budget.
ii - Within the first week following execution of the Agreement, meet with the DISTRICT and its representatives to prepare a detailed task analysis and work plan for documentation in a computer-computer- generated project schedule.
iii - This task analysis and work plan will identify specific tasks including, but not limited to: ♦ ◆ interviews, ♦ ◆ data collection ♦ ◆ analysis, ♦ ◆ report preparation, ♦ ◆ planning, ♦ ◆ Architectural programming, concepts and schematic design preparation and estimating that are part of the work of the Project. Also identified will be milestone activities or dates, specific task responsibilities, required completion times necessary for the review and approval by the DISTRICT and by all regulatory agencies and additional definition of deliverables.
iv - Participate in a general Project kick-off meeting to include the ARCHITECT, appropriate sub-sub- consultants, and DISTRICT staff.
v - The project kick-off meeting will introduce key team members from the DISTRICT and the ARCHITECT to each other, defining roles and responsibilities relative to the Project.the
vi - Identify and review pertinent information and/or documentation necessary from the DISTRICT for the completion of the Project.
vii - Review and explain the overall project goals, general approach, tasks, work plan and procedures and deliverable products of the Project.
viii - Review and explain the task analysis and Project work plan for all parties present; determine any adjustments or fine tuning that needs to be made to the work plan.
ix - Review documentation of the Project kick-off meeting prepared by the DISTRICT’S representative and comment prior to distribution.
x - Base Drawings and Site Survey Information
Appears in 1 contract
Samples: Agreement for Architectural Services