Project Scheduling. (a) Contractor shall develop a detailed "Initial City Schedule" for each City in the form provided by Contractor to Owner by letter dated April 30, 1999, which shall, at a minimum: (i) specify all major tasks required to complete the Work for such City, organized by Discipline, including the projected start and stop dates of such tasks; (ii) identify all Milestones related to such City set forth in Attachment 1.1 of Exhibit C (Contract Pricing, Payments and Milestone Achievement Criteria) of the Contract and the projected date of achieving such Milestones, (iii) identify all Key Tasks as set forth in Attachment 4 to this Exhibit B; and (iv) identify assumptions regarding completion in accordance with the schedule, including the performance of Owner's Responsibilities as set forth in Attachment 2 hereof and the receipt of third party / governmental approvals, Site Lease Agreements and similar items. For each City, the applicable Initial City Schedule shall require that Acceptance of such City be completed on or before the Acceptance Date and shall otherwise conform substantially to the Master Schedule attached hereto as Attachment 3. Contractor shall provide Owner with the Initial City Schedule for each City on or before forty-five (45) Calendar Days after EDC. The Initial City Schedule shall be subject to Owner's review and approval. (b) For each City, Contractor shall prepare a monthly City Progress Schedule showing the actual progress of the Work for such City against the applicable Initial City Schedule and shall submit such City Progress Schedule as part of the Monthly Status Report described in Section 2.6 below.
Appears in 3 contracts
Samples: Contract for Engineering and Construction (Xm Satellite Radio Holdings Inc), Contract for Engineering and Construction (Xm Satellite Radio Holdings Inc), Contract for Engineering and Construction of Terrestrial Repeater Network System (Xm Satellite Radio Holdings Inc)
Project Scheduling. (a) Contractor shall develop a detailed "Initial City Schedule" for each City in the form provided by Contractor to Owner by letter dated April 30, 1999, which shall, at a minimum: (i) specify all major tasks required to complete the Work for such City, organized by Discipline, including the projected start and stop dates of such tasks; (ii) identify all Milestones related to such City set forth in Attachment 1.1 of Exhibit C (Contract Pricing, Payments and Milestone Achievement Criteria) of the Contract and the projected date of achieving such Milestones, (iii) identify all Key Tasks as set forth in Attachment 4 to this Exhibit B; and (iv) identify assumptions regarding completion in accordance with the schedule, including the performance of Owner's Responsibilities as set forth in Attachment 2 hereof and the receipt of third party / governmental approvals, Site Lease Agreements and similar items. For each City, the applicable Initial City Schedule shall require that Acceptance of such City be completed on or before the Acceptance Date and shall otherwise conform substantially to the Master Schedule attached hereto as Attachment 3. Contractor shall provide Owner with the Initial City Schedule for each City on or before forty-five (45) Calendar Days after EDC. The Initial City Schedule shall be subject to Owner's review and approval.
(b) For each City, Contractor shall prepare a monthly City Progress Schedule showing the actual progress of the Work for such City against the applicable Initial City Schedule and shall submit such City Progress Schedule as part of the Monthly Status Report described in Section 2.6 below.
Appears in 1 contract