Common use of Protection of Site from encroachments Clause in Contracts

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 78 contracts

Samples: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Construction Contract

AutoNDA by SimpleDocs

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 32 contracts

Samples: Engineering, Procurement and Construction Agreement, Construction Contract, Epc Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 22 contracts

Samples: Engineering Procurement and Construction Agreement, Contract Agreement, Engineering Procurement and Construction Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Provisional Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat interest over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 14 contracts

Samples: Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment noencroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 5 contracts

Samples: Contract Agreement, Contract Agreement, Construction Contract

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Provisional Certificate, the Contractor shall maintain a round-the-the- clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat interest over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 4 contracts

Samples: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-Sub- contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 3 contracts

Samples: Draft Contract Agreement, Contract Agreement, Contract Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred memorandumreferred to in Clause 8.28.2.1, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 2 contracts

Samples: Epc Agreement, Epc Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Certificate, the Contractor shall maintain a round-round- the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site with safe & sound fencing and from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority Employer and undertake its removal at its own cost and expenses.

Appears in 2 contracts

Samples: Epc Agreement, Engineering, Procurement and Construction Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority Employer and undertake its removal at its own cost and expenses.

Appears in 2 contracts

Samples: Epc Agreement, Contract Agreement for Design and Construction

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.29.2.1, and until the issue of the Completion Provisional Certificate, the Contractor Concessionaire shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor Concessionaire shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat interest over all or any part of the Site or the Project Assets, or on any rights of the Contractor Concessionaire therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor Concessionaire shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or and / or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Provisional Certificate, the Contractor shall maintain a round-the-the- clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat interest over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 2 contracts

Samples: Epc Agreement, Epc Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction PeriodPeriod and until the issue of the Completion Certificate, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Contract Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Certificate, the Contractor shall maintain a round-round- the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority Employer and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Epc Agreement

AutoNDA by SimpleDocs

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx vigil over the Site and shall ensure and procure that no encroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Construction Contract

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment P a g e | 48 takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-Sub- contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority Authority/GMDA and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in toin Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment noencroachment takes place thereon. During the Construction Period, the Contractor shall Contractorshall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through claimingthrough or under the Agreement to place or create any Encumbrance or security threat securitythreat over all or any part of the Site or the Project Assets, or on any rights of the Contractor theContractor therein or under this Agreement, save and except as otherwise expressly set expresslyset forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith forth with to the Authority and undertake under take its removal at its own cost and expenses.

Appears in 1 contract

Samples: Construction Contract

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority Employer and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Demonstration Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the forthwithtothe Authority and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.28.2.1, and until the issue completion of the Completion CertificateO&M Period, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure ensures that no encroachment thereon takes place thereonplace. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority Employer and undertake its removal at its Contractor’s own cost and expenses.

Appears in 1 contract

Samples: Epc Contract

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments encroachments, or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Agreement

Protection of Site from encroachments. On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock xxxxx over the Site and shall ensure and procure that no encroachment Encroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement