Quarterly Report Requirements. Subrecipients must submit quarterly progress reports (QPR) for open, large projects in Public Assistance, all Hazard Mitigation Grant Program, Building Resilient Infrastructure and Committees (BRIC), and Pre-Disaster Mitigation Grant projects using GMS. QPRs are due to TDEM the 15th of the month after the reporting period ends. The reporting period consists of 4 3-month periods: a. Quarter 1 (Q1): October – December b. Quarter 2 (Q2): January – March c. Quarter 3 (Q3): April – June d. Quarter 4 (Q4): July – September Failure to submit required QPRs that demonstrate appropriate project progress for two or more quarters, or Requests for Reimbursement (RFR) not submitted quarterly, can result in the withholding or de-obligation of funding for subrecipients until all QPRs are submitted to TDEM.