Recovery of Schedule Delays. If the Program Manager determines that the Project is one week or more behind schedule, per the approved Overall Project Schedule, the Program Manager shall so notify the Design-Builder in writing. Within seven days of the date of the Program Manager's notice, the Design-Builder shall deliver to the Program Manager and Owner a written plan explaining how the Design-Builder intends to bring the Project back on schedule. The Design-Builder's plan must provide sufficient detail to allow the Program Manager and Owner to determine the proposal's feasibility.
Appears in 15 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract