Release of Performance Security. 7.4.1 The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified. 7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 24 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement
Release of Performance Security. 7.4.1 The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 18 contracts
Samples: Engineering, Procurement and Construction Agreement, Contract Agreement, Contract Agreement
Release of Performance Security. 7.4.1 (i) The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period Period, whichever is later, under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 7 contracts
Samples: Contract Agreement, Contract Agreement, Construction Contract
Release of Performance Security. 7.4.1 The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period Period, whichever is later, under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 5 contracts
Samples: Contract Agreement, Engineering Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Release of Performance Security. 7.4.1 The Authority Employer shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority Employer shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 3 contracts
Samples: Epc Agreement, Epc Contract, Contract Agreement for Design and Construction
Release of Performance Security. 7.4.1 The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. 30 Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 2 contracts
Samples: Draft Contract Agreement, Contract Agreement
Release of Performance Security. 7.4.1 (i) The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period Period, whichever is later, under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 (ii) The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.under
Appears in 2 contracts
Samples: Contract Agreement, Contract Agreement
Release of Performance Security. 7.4.1 The Authority Employer shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority Employer shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Samples: Demonstration Agreement
Release of Performance Security. 7.4.1 The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Samples: Draft Agreement for RFP for Beautification of Streets
Release of Performance Security. 7.4.1 The Authority Employer shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority Employer shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Samples: Epc Agreement
Release of Performance Security. 7.4.1 (i) The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period Period, whichever is later, under this Agreement. Notwithstanding the aforesaid, the Parties Draft Contract AgreementPage 49 of 261 S-D Tunnel 2022 agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Samples: Construction Contract
Release of Performance Security. 7.4.1 (i) The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period Period, whichever is later, under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security Improvement and widening to the Contractor within 28 (twenty eight) days two lane with paved shoulder of road from the date of issue of Completion Certificate under Article 12 of this Agreement.Km 21.100 to Km
Appears in 1 contract
Samples: Contract Agreement
Release of Performance Security. 7.4.1
(i) The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period Period, whichever is later, under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Samples: Construction Contract
Release of Performance Security. 7.4.1 The Authority shall return the 7.5.1 Performance Security shall be released/ refunded to the Contractor within after 60 (sixty) days of the later of the expiry of the Maintenance Period or the 3 years O&M period/Defects Liability Period under this Agreement. Period.
7.5.2 Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 . The Contractor shall furnish fresh Bank Guarantee for reduced amount of Performance Security, as appropriate in accordance with aforesaid provision under this Clause 7.5.1 to enable the Authority shall return to release the Additional existing Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreementavailable with it.
Appears in 1 contract
Samples: Contract Agreement
Release of Performance Security. 7.4.1 The Authority Authority/GMDA shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority Authority/GMDA shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Release of Performance Security. 7.4.1 (i) The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period Period, whichever is later, under this Agreement. Notwithstanding the aforesaid, the Parties Draft Contract AgreementPage 49 of 261 V-S Tunnel 2022 agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Samples: Draft Contract Agreement
Release of Performance Security.
7.4.1 The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Samples: Construction Contract
Release of Performance Security. 7.4.1 The Authority shall return the 7.5.1 Performance Security shall be released/ refunded to the Contractor within after 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Period.
7.5.2 Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 . The Contractor shall furnish fresh Bank Guarantee for reduced amount of Performance Security, as appropriate in accordance with aforesaid provision under this Clause 7.5.1 to enable the Authority shall return to release the Additional existing Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreementavailable with it.
Appears in 1 contract
Samples: Draft Contract Agreement
Release of Performance Security. 7.4.1 The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the later of the expiry of the Maintenance Period or the Defects Liability Period under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.
7.4.2 . The Authority shall return the Additional Performance Security to the Contractor within 28 (twenty eight) days from the date of issue of Completion Certificate under Article 12 of this Agreement.
Appears in 1 contract
Samples: Epc Agreement