Right to Observe Testing. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The other Party has the right, at its own expense, to observe such testing.
Appears in 90 contracts
Samples: Surplus Large Generator Interconnection Agreement, Surplus Large Generator Interconnection Agreement, Generator Interconnection Agreement
Right to Observe Testing. Each Party shall notify the other Party Parties in advance of its performance of tests of its Interconnection Facilities. The other Party has Parties shall each have the right, at its own expense, to observe such testing.
Appears in 75 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Right to Observe Testing. Each Party shall notify the System Operator and other Party Party(ies) in advance of its performance of tests of its Interconnection Facilities. The other Party Party(ies) has the right, at its own expense, to observe such testing.
Appears in 22 contracts
Samples: Interconnection Agreement, Via Electronic Filing, Interconnection Agreement
Right to Observe Testing. Each Party shall notify the other Party Parties in advance of its performance of tests of its Interconnection Facilities. The other Party has Parties have the right, at its own expense, to observe such testing.
Appears in 20 contracts
Samples: Distribution Facilities Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Right to Observe Testing. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The other Party has the right, at its own expense, to observe such testing.testing.β
Appears in 3 contracts
Samples: Agreement, Clustering Large Generator Interconnection, Large Generator Interconnection Agreement
Right to Observe Testing. Each Party shall, at its own expense, have the right to observe the testing of any of the other Party's assets whose performance may reasonably be expected to affect the reliability of the observing Party's assets. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The assets, and the other Party has the right, at its own expense, to observe may have a representative attend and be present during such testing.
Appears in 3 contracts
Samples: Generator Interconnection Agreement (ITC Holdings Corp.), Generator Interconnection Agreement (ITC Holdings Corp.), Generator Interconnection Agreement (ITC Holdings Corp.)
Right to Observe Testing. Each Party shall notify the System Operator and other Party Parties in advance of its performance of tests of its Interconnection Facilities. The other Party has Parties have the right, at its their own expense, to observe such testing.
Appears in 1 contract
Right to Observe Testing. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The other Party has the right, at its own expense, right to observe such testing.. Costs associated with this Article are subject to the relevant provisions of Rule 21.β
Appears in 1 contract
Samples: Generator Interconnection Agreement
Right to Observe Testing. Each Party shall, at its own expense, have the right to observe the testing of any of the other Party's facilities and equipment whose performance may reasonably be expected to affect the reliability of the observing Party's facilities and equipment. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The facilities and equipment, and the other Party has the right, at its own expense, to observe may have a representative attend and be present during such testing.
Appears in 1 contract
Samples: Connection and Operating Agreement
Right to Observe Testing. Each The Party performing the testing shall notify the other Party Parties in advance of its performance of tests of its Interconnection Facilitiesthe Upgrades. The Each of the other Party has Parties shall have the right, at its own expense, to observe such testing.
Appears in 1 contract
Samples: Upgrade Construction Agreement
Right to Observe Testing. Each Party shall, at its own expense, have the right to observe the testing of any of the other Party's Interconnection Facilities whose performance may reasonably be expected to affect the reliability of the observing Party's facilities and equipment. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The , and the other Party has the right, at its own expense, to observe may have a representative attend and be present during such testing.
Appears in 1 contract
Right to Observe Testing. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The other Party has the right, at its own expense, to observe such testing.. 36
Appears in 1 contract
Samples: Interconnection Agreement
Right to Observe Testing. Each Party shall notify the other Party in advance of its performance of tests of its Interconnection Facilities. The other Party has the right, at its own expense, right to observe such testing. Costs associated with this Article are subject to the relevant provisions of Rule 21.
Appears in 1 contract
Samples: Generator Interconnection Agreement