Safety Measures. The contractor shall take all necessary precautions for the safety of the workers and preserving their health while working on such jobs as required special protection and precaution wherever required. The following are some of the requirements listed though not exhaustive. The contractor shall also comply with the directions issued by the Engineer in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustive) (1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth. (2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above. (3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around etc. (4) Providing workmen with proper safety belts, ropes, etc. when working on any masts, cranes, circle hoist, dredges etc. (5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc. (6) Preventing over loading and over crowding of floating the land based machinery and equipment. (7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping the boats with adequate numbers of life boats etc. (8) Avoiding bare xxxx xxxxx etc. as would cause electrocution to workers. (9) Making all platforms, stagings and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks. (10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries. (11) Taking the all-necessary precautions wherever divers are engaged on work. (12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring of the labourers in the opinion of the Engineer-in -charge
Appears in 4 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Safety Measures. The contractor shall take all necessary precautions for the safety of the workers and preserving their health while working on such jobs as required special protection and precaution wherever required. The following are some of the requirements listed though not exhaustive. The contractor shall also comply with the directions issued by the Engineer in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustive)
(1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth.
(2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above.
(3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around etc.
(4) Providing workmen with proper safety belts, ropes, etc. when working on any masts, cranes, circle hoist, dredges etc.
(5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc.
(6) Preventing over loading and over crowding of floating the land based machinery and equipment.
(7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping the boats with adequate numbers number of life boats jackets etc.
(8) Avoiding bare xxxx xxxxx etc. as would cause electrocution to workers.
(9) Making all platforms, stagings staging and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks.
(10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries.
(11) Taking the all-necessary precautions wherever divers are engaged on work.
(12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto up to knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring of the labourers in the opinion of the Engineer-in -charge
Appears in 3 contracts
Samples: Original Agreement, Construction Contract, Construction Contract
Safety Measures. The contractor shall take all necessary precautions for the safety of the workers and preserving their health while working on such jobs as required special protection and precaution wherever required. The following are some of the requirements listed though not exhaustive. The contractor shall also comply with the directions issued by the Engineer in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustive)
(1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth.
(2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above.
(3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around etc.
(4) Providing workmen with proper safety belts, ropes, etc. when working on any masts, cranes, circle hoist, dredges etc.
(5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc.
(6) Preventing over loading and over crowding of floating the land based machinery and equipment.
(7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping the boats with adequate numbers of life boats etc.
(8) Avoiding bare xxxx xxxxx etc. as would cause electrocution to workers.
(9) Making all platforms, stagings and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks.
(10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries.
(11) Taking the all-necessary precautions wherever divers are engaged on work.
(12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring of the labourers in the opinion of the Engineer-in -charge-charge 21 Medical and sanitary arrangements to be provided for labour employed in the
(a) The contractor shall provide an adequate supply of pure and wholesome water for the use of labourers on works and in camps.
(b) The contractor shall construct trenches. Semi permanent latrines for the use of
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Safety Measures. The contractor shall take all necessary precautions for the safety of the workers and preserving their health while working on such jobs as required special protection and precaution wherever required. The following are some of the requirements listed though not exhaustive. The contractor shall also comply with the directions issued by the Engineer in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustive)
(1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth.
(2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above.
(3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around etc.
(4) Providing workmen with proper safety belts, ropes, etc. when working on any masts, cranes, circle hoist, dredges etc.
(5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc.
(6) Preventing over loading and over crowding of floating the land based machinery and equipment.
(7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping , equipping the boats with adequate numbers number of life boats etc.
(8) Avoiding bare xxxx xxxxx etc. as would cause electrocution to workers.
(9) Making all platforms, stagings and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks.
(10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries.
(11) Taking the all-necessary precautions wherever divers are engaged on work.
(12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring of the labourers in the opinion of the Engineer-in -charge
Appears in 2 contracts
Samples: Contract Agreement, Construction Contract
Safety Measures. a. The contractor shall take all necessary precautions should deploy minimum one qualified safety supervisor for the safety site work.
b. The contractor should submit the Job Hazard Analysis (XXX) for approval before start of work at site.
c. All personnel of the contractors shall undergo Industrial safety training to be impart by NPCIL.
d. All the workers and preserving their health while working on such jobs as should be provided with Personal Protective Equipment (PPE) conforming to relevant Indian standards required special protection and precaution wherever required. The following are some to be used during execution of the requirements listed though not exhaustive. The contractor shall also comply with the directions issued work by the Engineer contractor.
e. Height work permit shall be obtained for all the works carried out on temporary staging, platforms etc. above a height of 3.5 meters from stable floor or ground floor. All implements used for height work such as scaffold, access stairs/ladders, platform, railings etc should be certified by concerned engineer prior to its use and to the effect that they should have a display as “Safe for use”. Wood, bamboo or other combustible materials shall not be used for making staging/scaffolds
f. For carrying out work at height of more than 3.5 meters above floor/ground level, height pass should be provided for all the workers involved in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustive)
(1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth.
(2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above.
(3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around which includes ascertaining medical fitness by Registered Medical Practitioner and worker’s physical test etc.
g. During the execution of the work, the contractor shall deploy minimum one qualified and licensed electrician. Minimum qualification for such electrician shall be ITI in electrical trade. He should also possess electrician/xxxxxxx license issued by concerned state government authority.
h. Sufficient numbers of Portable fire extinguishers (4DCP or CO2) Providing workmen with proper safety beltsshall be provided in the vicinity of all power distribution boards.
i. All power distribution boards, ropeselectrically operated equipment/tools, cables, power extension boards etc. when working shall be inspected periodically for ensuring their healthiness. Inspection stickers shall be affixed on any masts, cranes, circle hoist, dredges etcall such equipment/tools.
(5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc.
(6) Preventing over loading and over crowding of floating the land based machinery and equipment.
(7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping the boats with adequate numbers of life boats etc.
(8) Avoiding bare xxxx xxxxx etc. as would cause electrocution to workers.
(9) Making all platforms, stagings and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks.
(10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries.
(11) Taking the all-necessary precautions wherever divers are engaged on work.
(12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring of the labourers in the opinion of the Engineer-in -charge
Appears in 1 contract
Samples: Purchase Order
Safety Measures. The contractor shall take all necessary precautions for the safety of the workers and preserving their health while working on such jobs as required special protection and precaution wherever required. The following are some of the requirements listed though not exhaustive. The contractor shall also comply with the directions issued by the Engineer in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustive)
(1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth.
(2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above.
(3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around etc.
(4) Providing workmen with proper safety belts, ropes, etc. when working on any masts, cranes, circle hoist, dredges etc.
(5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc.
(6) Preventing over loading and over crowding of floating the land based machinery and equipment.
(7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping the boats with adequate numbers of life boats etc.
(8) Avoiding bare xxxx xxxxx etc. as would cause electrocution to workers.
(9) Making all platforms, stagings and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks.
(10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries.
(11) Taking the all-necessary precautions wherever divers are engaged on work.
(12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring of the labourers in the opinion of the Engineer-in -charge-charge 21 Medical and sanitary arrangements to be provided for labour employed in the
(a) The contractor shall provide an adequate supply of pure and wholesome water for the use of labourers on works and in camps.
(b) The contractor shall construct trenches. Semi permanent latrines for the use of labourers. Separate latrine shall be provided for men and women.
(c) The contractor shall build sufficient number of huts on suitable plot of land for use of the labourers according to the following specifications.
(1) Huts of bamboos and grass may be constructed.
(2) There should be no over crowding. Floor space at the rate of 3 Sqm(30 Sq.ft.) per head shall is provided. Care should be taken to see that the huts are kept clean and in good order.
(3) The contractor must find his own land. If he wants Xxxx.xxxx he should apply for it. Assessment for it if demanded will be payable by contractor. However the Department does not bind itself for making available the required land.
(4) A good site not liable to submergence shall be selected on high ground remote from jungle but well provided with trees; shall be chosen wherever it is available. The neighborhood of tank, jungles, trees or xxxxx should be particularly avoided. Camps should not be established close to large cutting of earthwork.
(5) The lines of huts shall have open space of at least 10 meters between rows. When a good natural site cannot be procured particular attention should be given to the drainage.
(d) The contractor shall construct sufficient number of bathing places, sufficient number of washing places also be provided for the purpose of the washing cloths.
(e) The contractor shall make sufficient arrangement for draining away the surface and suage water as well as water from the bathing and washing places and shall dispose of the waste water in such away as not cause any nuisance.
(f) The contractor shall engage a medical officer with a traveling dispensary for a camp containing 500 or more person if there is no Government or other dispensary situated within eight Kilometers from the camp. In case of an emergency contractor shall at his cost, free transport for quick medical help to his sick workers..
(g) The contractor shall provide the necessary staff for affecting the satisfactory conservancy and cleanliness of the camp to the satisfaction of the Engineer -in charge .At least one sweeper per 200 person should engaged.
(h) The Assistant Director of public health shall be consulted before opening a labour camp and his instruction on matters such as water supply, sanitary, convenience, the camp site, accommodation and food supply shall be followed by the contractor.
(i) In addition to above all provision of the relevant labour act pertaining to basic amenities to be provide to the labour shall be applicable which will be arranged by the contractor
(j) The contractor shall make arrangement for all anti malaria measures to be provided for the labour employed on the work. The anti malaria measures shall be as directed by the Public Health Officer.
Appears in 1 contract
Samples: Construction Contract
Safety Measures. The contractor shall take all necessary precautions for the safety of the workers and preserving their health while working on such jobs as required special protection and precaution wherever required. The following are some of the requirements listed though not exhaustive. The contractor shall also comply with the directions issued by the Engineer in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustive)
(1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth.
(2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above.
(3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around etc.
(4) Providing workmen with proper safety belts, ropes, etc. when working on any masts, cranes, circle hoist, dredges etc.
(5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc.
(6) Preventing over loading and over crowding of floating the land based machinery and equipment.
(7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping the boats with adequate numbers of life boats etc.
(8) Avoiding bare xxxx xxxxx etc. as would cause electrocution to workers.
(9) Making all platforms, stagings and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks.
(10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries.
(11) Taking the all-necessary precautions wherever divers are engaged on work.
(12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring of the labourers in the opinion of the Engineer-in -charge-charge 21 Medical and sanitary arrangements to be provided for labour employed in the construction by the contractor.
(a) The contractor shall provide an adequate supply of pure and wholesome water for the use of labourers on works and in camps.
(b) The contractor shall construct trenches. Semi permanent latrines for the use of labourers. Separate latrine shall be provided for men and women.
(c) The contractor shall build sufficient number of huts on suitable plot of land for use of the labourers according to the following specifications.
(1) Huts of bamboos and grass may be constructed.
(2) There should be no over crowding. Floor space at the rate of 3 Sqm(30 Sq.ft.) per head shall is provided. Care should be taken to see that the huts are kept clean and in good order.
(3) The contractor must find his own land. If he wants Xxxx.xxxx he should apply for it. Assessment for it if demanded will be payable by contractor. However the Department does not bind itself for making available the required land.
(4) A good site not liable to submergence shall be selected on high ground remote from jungle but well provided with trees; shall be chosen wherever it is available. The neighborhood of tank, jungles, trees or xxxxx should be particularly avoided. Camps should not be established close to large cutting of earthwork.
(5) The lines of huts shall have open space of at least 10 meters between rows. When a good natural site cannot be procured particular attention should be given to the drainage.
(d) The contractor shall construct sufficient number of bathing places, sufficient number of washing places also be provided for the purpose of the washing cloths.
(e) The contractor shall make sufficient arrangement for draining away the surface and suage water as well as water from the bathing and washing places and shall dispose of the waste water in such away as not cause any nuisance.
(f) The contractor shall engage a medical officer with a traveling dispensary for a camp containing 500 or more person if there is no Government or other dispensary situated within eight Kilometers from the camp. In case of an emergency contractor shall at his cost, free transport for quick medical help to his sick workers..
(g) The contractor shall provide the necessary staff for affecting the satisfactory conservancy and cleanliness of the camp to the satisfaction of the Engineer -in charge .At least one sweeper per 200 person should engaged.
(h) The Assistant Director of public health shall be consulted before opening a labour camp and his instruction on matters such as water supply, sanitary, convenience, the camp site, accommodation and food supply shall be followed by the contractor.
(i) In addition to above all provision of the relevant labour act pertaining to basic amenities to be provide to the labour shall be applicable which will be arranged by the contractor
(j) The contractor shall make arrangement for all anti malaria measures to be provided for the labour employed on the work. The anti malaria measures shall be as directed by the Public Health Officer.
Appears in 1 contract
Samples: Construction Contract
Safety Measures. The contractor shall take all necessary precautions for the safety of the workers and preserving their health while working on such jobs as required special protection and precaution wherever required. The following are some of the requirements listed though not exhaustive. The contractor shall also comply with the directions issued by the Engineer in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustive)
(1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth.
(2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above.
(3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around etc.
(4) Providing workmen with proper safety belts, ropes, etc. when working on any masts, cranes, circle hoist, dredges etc.
(5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc.
(6) Preventing over loading and over crowding overcrowding of floating the land based machinery and equipment.
(7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping , equipping the boats with adequate numbers number of life boats etc.
(8) Avoiding bare xxxx xxxxx etc. as would cause electrocution to workers.
(9) Making all platforms, stagings and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks.
(10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries.
(11) Taking the all-necessary precautions wherever divers are engaged on work.
(12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring being of the labourers in the opinion of the Engineer-in -charge–charge
Appears in 1 contract
Samples: Tender Agreement
Safety Measures. The contractor shall take all necessary precautions for the safety of the workers and preserving their health while working on such jobs as required special protection and precaution wherever required. The following are some of the requirements listed though not exhaustiveexhaustVe. The contractor shall also comply with the directions issued by the Engineer in this behalf from time to time at all times. The following are some of the requirements (The list is not exhaustiveexhaustVe)
(1) Providing protective footwear to workers in situations like mixing and placing of mortar of concrete, in quarries and place where the work is to be done under too much wet conditions as also for movements over surfaces tested with oyster growth.
(2) Providing protective headwear to workers in quarries etc. to protect them against accidental fall of materials from above.
(3) Providing handrails to the edges of the loading platforms of barrages ropeways, ladders not allowing rails of metal parts or unless timber to spread around etc.
(4) Providing workmen with proper safety belts, ropes, etc. when working on any masts, cranes, circle hoist, dredges etc.
(5) Taking necessary steps towards training the workers concerned of the use of machinery before they are allowed to handle it independently and taking all necessary precautions in and around the areas where machines, hoists and similar units are working. Wherever required by the law the persons handling the machinery shall have the required license, certificate etc.
(6) Preventing over loading and over crowding of floating the land based machinery and equipment.
(7) Providing life belts to all men working at such situations from where they may accidentally fall into water. Equipping the boats with adequate numbers of life boats etc.
(8) Avoiding bare xxxx xxxxx lVe wires etc. as would cause electrocution to workers.
(9) Making all platforms, stagings and temporary structures sufficiently strong and not causing the workmen and supervisory staff to take undue risks.
(10) Providing sufficient first aid trained staff and equipment to be available quickly at the work site to render immediate first-aid treatment in case of accident due to suffocation, drowning and other injuries.
(11) Taking the all-necessary precautions wherever divers dVers are engaged on work.
(12) Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover the chest and back reaching upto knees, plain goggles for the eyes to the labour working with hot asphalt, handling, vibrators in cement concrete and also where use of any or all these items is, essential in the interest of health and well-bring of the labourers in the opinion of the Engineer-in -charge–charge
Appears in 1 contract
Samples: Construction Contract