Common use of Schedule Adjustment Clause in Contracts

Schedule Adjustment. If the CM and its Contractors, for reasons beyond their control, are delayed in beginning any activity, the CM shall, nevertheless, have the same number of days as is shown in the Master Schedule for the activity, and the completion date of the affected activity and any succeeding activity that is dependent upon that activity shall be adjusted accordingly; provided that at any time the Owner, by means of a change order, may require the CM to work overtime, to increase labor forces or to take any necessary or appropriate action to decrease the time required for any activity, and the CM shall be entitled to an adjustment in the GMP computed in accordance with this Agreement. The CM shall review the contents of a request for changes to the construction contract time or price submitted by a Contractor, assemble information concerning the request and endeavor to determine the cause of the request. In instances where the CM’s analysis reveals that the request is valid, the CM shall prepare a detailed report to the Designer and the Owner for review, consideration and approval. The CM shall, prior to the issuance of a change order, determine the effect on the Master Schedule of time extensions requested by the Contractor. The Designer shall prepare the necessary change order documents for signing by the CM, Designer and Owner. The CM shall then prepare the necessary documents to effect a change to the contract with the Contractor.

Appears in 3 contracts

Samples: Architect Contract, Construction Management Agreement, Construction Management Agreement

AutoNDA by SimpleDocs

Schedule Adjustment. If the CM and its Contractors, for reasons beyond their control, are delayed in beginning any activity, the CM shall, nevertheless, have the same number of days as is shown in the Master School Project Schedule for the activity, and the completion date of the affected activity and any succeeding activity that is dependent upon that activity shall be adjusted accordingly; provided that at any time the Owner, by means of a change order, may require the CM to work overtime, to increase labor forces or to take any necessary or appropriate action to decrease the time required for any activity, and the CM shall be entitled to an adjustment in the GMP computed in accordance with this Agreement. The CM shall review the contents of a request for changes to the construction contract time or price submitted by a Contractor, assemble information concerning the request and endeavor to determine the cause of the request. In instances where the CM’s analysis reveals that the request is valid, the CM shall prepare a detailed report to the Designer and the Owner for review, consideration and approval. The CM shall, prior to the issuance of a change order, determine the effect on the Master School Project Schedule of time extensions requested by the Contractor. The Designer shall prepare the necessary change order documents for signing by the CM, Designer and Owner. The CM shall then prepare the necessary documents to effect a change to the contract with the Contractor.

Appears in 1 contract

Samples: Architect Contract

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!