Service Schedule. 2.8.1 The CONSULTANT shall perform its services expeditiously. The CONSULTANT shall submit for the CITY’S approval a schedule for the performance for the CONSULTANT’S services which shall include allowance for time required for the CITY’S review of submissions and for approvals of authorities have jurisdiction over the Project. The CITY shall review and approve or reject any schedules submitted by the CONSULTANT within five (5) working days of said submittal. If, in the event that construction of the Project is suspended for more than thirty (30) days, the CONSULTANT shall also suspend Construction Administration Services upon request of CITY. Any time spent on the Project at the request of the CITY or on the CITY’S behalf during this suspension shall be additional services and shall be paid based on the Standard Hourly Rates attached to this contract. The reasonable term of construction upon which the fees for Construction Administration in this contract are based, shall be extended to include the period of construction suspension. This schedule, when approved by the CITY, shall not, except for cause, be exceeded by the CONSULTANT. In the event the CITY rejects any schedules submitted by the CONSULTANT, the CONSULTANT shall submit a revised schedule within forty-eight (48) hours of said rejection. Submission of a schedule acceptable to the CITY and to which the CITY makes no objection shall be a condition precedent for any payment to the CONSULTANT. 2.8.2 Upon receipt of the Notification of Commencement and the fully executed Purchase Order, the CONSULTANT shall commence services to the CITY on the Commencement Date, and shall continuously perform services to the CITY, without interruption, in accordance with the time frames set forth in the “Project Schedule,” a copy of which is attached and incorporated into this Agreement as EXHIBIT “B”. The number of calendar days from the Commencement Date, through the date set forth in the Project Schedule for completion of the Project or the date of actual completion of the project, which ever shall last occur, shall constitute the Contract Time.
Appears in 1 contract
Samples: Project Agreement
Service Schedule. 2.8.1 The CONSULTANT shall perform its services expeditiously. The CONSULTANT shall submit for the CITY’S approval a schedule for the performance for the CONSULTANT’S services which shall include allowance for time required for the CITY’S review of submissions and for approvals of authorities have jurisdiction over the Project. The CITY shall review and approve or reject any schedules submitted by the CONSULTANT within five (5) working days of said submittal. If, in the event that construction of the Project is suspended for more than thirty (30) days, the CONSULTANT shall also suspend Construction Administration Services upon request of CITY. Any time spent on the Project at the request of the CITY or on the CITY’S behalf during this suspension shall be additional services and shall be paid based on the Standard Hourly Rates attached to this contract. The reasonable term of construction upon which the fees for Construction Administration in this contract are based, shall be extended to include the period of construction suspension. This schedule, when approved by the CITY, shall not, except for cause, be exceeded by the CONSULTANT. In the event the CITY rejects any schedules submitted by the CONSULTANT, the CONSULTANT shall submit a revised schedule within forty-eight (48) hours of said rejection. Submission of a schedule acceptable to the CITY and to which the CITY makes no objection shall be a condition precedent for any payment to the CONSULTANT.
2.8.2 Upon receipt of the Notification of Commencement and the fully executed Purchase Order, the CONSULTANT shall commence services to the CITY on the Commencement Date, and shall continuously perform services to the CITY, without interruption, in accordance with the time frames set forth in the “Project Schedule,” a copy of which is attached and incorporated into this Agreement as EXHIBIT “B”. The number of calendar days from the Commencement Date, through the date set forth in the Project Schedule for completion of the Project or the date of actual completion of the project, which ever shall last las occur, shall constitute the Contract Time.
2.8.3 Liquidated Damages: NOT USED
2.8.4 No Damages for Delay: The CONSULTANT shall not be entitled to any claim for damages including, but not limited to , loss of profits, loss of use, home office overhead expenses, equipment rental and similar costs on account of delays in the progress of the Project from any cause or national disaster or emergency, unusual delay in deliveries, unusual delay in procuring permits, differing site conditions, unavoidable casualties or other cause beyond the CONSULTANT’S control, or by delay authorized by the CITY, or by other causes which the CONSULTANT determines may justify delay. The CONSULTANT’S sole recovery and remedy for any such delay shall be a reasonable extension of time and a revision to the Project Schedule as determined by the CITY. However, additional costs to the CONSULTANT or delays in the CONSULTANT’S performance caused by improperly time activities shall not be the basis for granting a time extension. If the CONSULTANT wishes to make a claim for an increase in time of performance, written notice of such claim shall be made to the CITY within ten (10) working days after the occurrence of the event, or the first appearance of the condition giving rise to such claim. The CITY’S representative shall determine whether or not the CONSULTANT is entitled to a time extension for the delay. The failure of the CONSULTANT to give such notice shall constitute a waiver of any claim under this section.
2.8.5 Notwithstanding the provisions of paragraph 2.8.4, in the event that the Contractor fails to substantially complete the Project on or before the substantial completion date specified in the Contract for Construction or the Contractor is granted an extension of the time to complete performance under the Contract for Construction and the CONSULTANT’S contract administration services are materially extended by the CITY as a direct result thereof and through no fault of the CONSULTANT, the CONSULTANT shall be entitled to additional compensation at the rates shown in the Continuing Services Agreement EXHIBIT “A”. The amount of compensation due by the CONSULTANT under this paragraph shall be pursuant to an approved Amendment to the Project Agreement
Appears in 1 contract
Samples: Project Agreement
Service Schedule. 2.8.1 2.9.1 The CONSULTANT shall perform its services expeditiouslyin accordance with agreed upon schedule. The CONSULTANT shall submit for the CITY’S ’s approval a schedule for the performance for the CONSULTANT’S ’s services which that shall include allowance for time required for the CITY’S ’s review of submissions and for approvals of authorities have jurisdiction over the Project. The CITY shall review and approve or reject any schedules submitted by the CONSULTANT within five (5) working days of said submittal. If, in the event that construction of the Project is suspended for more than thirty (30) days, the CONSULTANT shall also suspend Construction Administration Services upon request of the CITY. Any time spent on the Project at the request of the CITY or on the CITY’S ’s behalf during this suspension shall be additional services and shall be paid based on the Standard Hourly Rates attached to this contractthe Continuing Services Agreement as EXHIBIT “B” Hourly Rates. The reasonable term of construction upon which the fees for Construction Administration Services in this contract Agreement are based, shall be extended to include the period of construction suspension. This schedule, when approved by the CITY, shall not, except for cause, be exceeded by the CONSULTANT. In the event the CITY rejects any schedules submitted by the CONSULTANT, the CONSULTANT shall submit a revised schedule within forty-eight (48) hours of said rejection. Submission of a schedule acceptable to the CITY and to which the CITY makes no objection shall be a condition precedent for any payment to the CONSULTANT.
2.8.2 2.9.2 Upon receipt of the Notification of Commencement and the fully executed Purchase Order, the CONSULTANT shall commence services to the CITY on the Commencement Date, and shall continuously perform services to the CITY, without interruption, in accordance with the time frames set forth in the “Project Schedule,” a copy of which is attached and incorporated into this Agreement as EXHIBIT “B”. 2.” The number of calendar days from the Commencement Date, through the date set forth in the Project Schedule for completion of the Project or the date of actual completion of the projectProject, which ever shall last occur, shall constitute the Contract Time.
Appears in 1 contract
Samples: Project Agreement
Service Schedule. 2.8.1 7.1 The CONSULTANT shall perform its services expeditiously. The CONSULTANT shall submit for shall, when requested by the CITY’S , submit to the CITY for approval a schedule for the performance for the CONSULTANT’S ’s services which shall include allowance for time required for the CITY’S ’s review of submissions and for approvals of authorities have having jurisdiction over the Project. The CITY shall review and approve or reject any schedules submitted by the CONSULTANT within five (5) 10 working days of said submittal. If, in the event that construction of the Project is suspended for more than thirty (30) days, the CONSULTANT shall also suspend Construction Administration Services upon request of CITY. Any time spent on the Project at the request of the CITY or on the CITY’S ’s behalf during this suspension shall be additional services and shall be paid based on the Standard Hourly Rates attached to this contract. The reasonable term of construction upon which the fees for Construction Administration in this contract are based, shall be extended to include the period of construction suspension. This schedule, when approved by the CITY, shall not, except for cause, be exceeded by the CONSULTANT. In the event the CITY rejects any schedules submitted by the CONSULTANT, the CONSULTANT shall submit a revised schedule within forty-eight two (482) hours business days of said rejection. Submission of a schedule acceptable to the CITY and to which the CITY makes no objection shall be a condition precedent for any payment to the CONSULTANT.CONSULTANT. SECTION 8 MISCELLANEOUS SERVICES – NOT USED EXHIBIT "3" TO PROJECT AGREEMENT INVERRARY BRIDGE FORCEMAIN RELOCATION DESIGN AND CONSTRUCTION MANAGEMENT SERVICES P R O J E C T S C H E D U L E Task/Description Task/Completion In Weeks Following Authorization
2.8.2 Upon receipt 1.3 Preliminary Design 16 94 1.4 - Final Design - 90% Design Submittal 28 106 - 100% Design Submittal 32 110 1.5 - Final Estimate of the Notification Cost of Commencement and the fully executed Purchase OrderConstruction 32 110 1.6 - Final Permit Application Documents 32 110 2.0 – Bidding Services (Includes 6 week bidding period) 38 148 3.0 – 6.0 Construction Contract Administration Services, the CONSULTANT shall commence services to the CITY on the Commencement DateInspection Services, and shall continuously perform services to the CITYSpecial Services, without interruption, in accordance with the time frames set forth in the “Project Schedule,” a copy & Service Schedule 92 170 P A Y M E N T S C H E D U L E Task/Description Percent of which is attached and incorporated into this Agreement as EXHIBIT “B”. The number of calendar days from the Commencement Date, through the date set forth in the Project Schedule for completion of the Project or the date of actual completion of the project, which ever shall last occur, shall constitute the Contract Time.Total Fee Fee 1.3 - Preliminary Design 37.4 35.7 $69,014 1.4 – Final Design - 90% Design Submittal 9.7 9.2 $17,770 - 100% Design Submittal 9.7 11.4 $17,770 $22,120