Project Managers The JBE’s project manager is: [Insert name]. The JBE may change its project manager at any time upon notice to Contractor without need for an amendment to this Agreement. Contractor’s project manager is: [Insert name]. Subject to written approval by the JBE, Contractor may change its project manager without need for an amendment to this Agreement.
Project Managers; Meetings 10.1 Promptly following the Effective Date, each Party shall designate a Project Manager responsible for coordinating the Party’s Work and shall provide the other Party with a written notice containing the name and contact information of such Project Manager (“Project Manager”). In no event shall any Project Manager be authorized to amend or modify the provisions of this Agreement. Each Party may change its Project Manager, from time to time, by written notice to the other Party.
CONSTRUCTION MANAGER’S SERVICES The services which the Construction Manager shall provide include, but are not limited to, those described or specified herein. The services described or specified shall not be deemed to constitute a comprehensive specification having the effect of excluding services not specifically mentioned.
Synchronisation Commissioning and Commercial Operation 8.1 The Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
Quality Management System Supplier hereby undertakes, warrants and confirms, and will ensue same for its subcontractors, to remain certified in accordance with ISO 9001 standard or equivalent. At any time during the term of this Agreement, the Supplier shall, if so instructed by ISR, provide evidence of such certifications. In any event, Supplier must notify ISR, in writing, in the event said certification is suspended and/or canceled and/or not continued.
Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.
Contract Managers Each party will designate a Contract Manager during the term of this Contract whose responsibility shall be to oversee the party's performance of its duties and obligations pursuant to the terms of this Contract. As of the effective date, Citizens’ and Vendor’s Contract Managers are as follows: Citizens’ Contract Manager Xxxx Xxx Citizens Property Insurance 0000 Xxxxxxxxx Xxx Xxxxxxxxxxxx, XX 00000 Phone: (000) 000-0000 Email: xxxx.xxx@xxxxxxxxxxx.xxx Xxxxx Xxxxxxxxxx Citizens Property Insurance 0000 Xxxxxxxxx Xxx Xxxxxxxxxxxx, XX 00000 Phone: (000) 000-0000 Email: Xxxxx.xxxxxxxxxx@xxxxxxxxxxx.xxx Vendor’s Contract Manager Xxxxxxx Xxxxxxxxx Level 4 Ventures, Inc. 00000 Xxxxx Xxxxx Xxxxx, XX 00000 000-000-0000 Xxxxxxx@xxxxx0xxxxxxxx.xxx
Project Management Plan 1 3.4.1 Developer is responsible for all quality assurance and quality control 2 activities necessary to manage the Work, including the Utility Adjustment Work.
Construction Manager’s Fee The following shall be deemed included in the Construction Manager’s fee for services during the Construction Phase.
Quality Management Grantee will: