SUBSTANTIAL COMPLETION CRITERIA Sample Clauses

SUBSTANTIAL COMPLETION CRITERIA. Substantial Completion shall mean that: (i) the Facility has achieved Mechanical Completion; (ii) Start-Up of the Facility has occurred; (iii) the Facility has been demonstrated during a Performance Test to meet the Minimum Performance Guarantees and Contractor has so certified to Owner pursuant to a Performance Test Certificate in accordance with the terms of Section 1.3 of Exhibit G; (iv) the Facility has met the requirements of the Steam Purity Test; (v) the Facility has met the requirements of the Reliability Test; (vi) completed turnover packages for all plant systems have been delivered to Owner; and (vii) all Punch List items, except those identified for completion after Substantial Completion, including those provided pursuant to Section 7.1 to be completed after Substantial Completion, have been completed.
AutoNDA by SimpleDocs
SUBSTANTIAL COMPLETION CRITERIA. Substantial Completion will be deemed to have been achieved when all of the following Substantial Completion Criteria have been satisfied: 1. Startup, commissioning, and the Performance Tests (as detailed in Section 4 of this Appendix F) have been completed in accordance with the Contract. 2. The Plant (i) is complete such that Company can commence operation of a fully-tested, integrated and operational Plant.
SUBSTANTIAL COMPLETION CRITERIA. The following enumerated requirements are the conditions precedent to the achievement of Substantial Completion (the “Substantial Completion Criteria”):
SUBSTANTIAL COMPLETION CRITERIA. The Parties recognize that the terms “Capacity”, “capacity”, “Power” and “power” are utilized interchangeably in this Appendix H and agree that such terms are synonymous as used herein. The Plant will be deemed ready for Substantial Completion when all of the following have occurred: 1. The Plant is substantially and materially complete and has been fully designed, constructed and equipped in accordance with the Agreement (except as provided in the Final Punch List). 2. All Governmental Approvals can be assigned or transferred in accordance with Article 2 of this Agreement. 3. All Equipment and systems are operational in accordance with this Agreement, including its Appendices. 4. All Owner-specified Performance, Commissioning and Functional Tests as detailed in Appendix B have been successfully completed. For the purposes of conducting Functional Tests , a “Start” shall be deemed to be the initiation of the start sequence. All activities required for these startup and shutdown tests shall be performed through the Plant's Distributed Control System (“DCS”) with the exception of any normally expected and routine action taken by an operator. The Plant's DCS shall control, or shall cause to be controlled, all Equipment necessary for the safe and reliable operation of the Plant with the exception of Equipment normally controlled manually.

Related to SUBSTANTIAL COMPLETION CRITERIA

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • COMMENCEMENT AND COMPLETION OF THE PROJECT Section 3.01 The Project (a) The Company intends and expects, together with any Sponsor Affiliate, to (i) construct and acquire the Project, and (ii) meet the Contract Minimum Investment Requirement within the Investment Period. The Company anticipates that the first Phase of the Project will be placed in service during the calendar year ending December 31, 2020. (b) Pursuant to the FILOT Act and subject to Section 4.03 hereof, the Company and the County hereby agree that the Company and any Sponsor Affiliates shall identify annually those assets which are eligible for FILOT payments under the FILOT Act and which the Company or any Sponsor Affiliate selects for such treatment by listing such assets in its annual PT-300S form (or comparable form) to be filed with the Department (as such may be amended from time to time) and that by listing such assets, such assets shall automatically become Economic Development Property and therefore be exempt from all ad valorem taxation during the Exemption Period. Anything contained in this Fee Agreement to the contrary notwithstanding, the Company and any Sponsor Affiliates shall not be obligated to complete the acquisition of the Project. However, if the Company, together with any Sponsor Affiliates, does not meet the Contract Minimum Investment Requirement within the Investment Period, the provisions of Section 4.03 hereof shall control. (c) The Company may add to the Land such real property, located in the same taxing District in the County as the original Land, as the Company, in its discretion, deems useful or desirable. In such event, the Company, at its expense, shall deliver an appropriately revised Exhibit A to this Fee Agreement, in form reasonably acceptable to the County.

  • Project Specific Milestones In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before December 31, 2020 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.2 Delivery of major electrical equipment. On or before December 31, 2021, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

  • Project/Milestones Taxpayer provides refrigerated warehousing and logistic distribution services to clients throughout the United States. In consideration for the Credit, Taxpayer agrees to invest in a new refrigeration and distribution facility in the XxXxxxxxx Park area of Sacramento, California, and hire full-time employees (collectively, the “Project”). Further, Taxpayer agrees to satisfy the milestones as described in Exhibit A (“Milestones”) and must maintain Milestones for a minimum of three (3) taxable years thereafter. In the event Taxpayer employs more than the number of full-time employees, determined on an annual full-time equivalent basis, than required in Exhibit A, for purposes of satisfying the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” Taxpayer may use the salaries of any of the full-time employees hired within the required time period. For purposes of calculating the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” the salary of any full-time employee that is not employed by Taxpayer for the entire taxable year shall be annualized. In addition, the salary of any full-time employee hired to fill a vacated position in which a full-time employee was employed during Taxpayer’s Base Year shall be disregarded.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: § 3.2 The Contract Time shall be measured from the date of commencement of the Work.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.