Suspension by the Owner for Convenience. 11.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. 11.3.2 The Contract Price and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Paragraph 11. 3.1. Adjustment of the Contract Price shall include profit. No adjustment shall be made to the extent: 11.3.2.1 that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or 11.3.2.2 that an equitable adjustment is made or denied under another provision of the Agreement.
Appears in 24 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Suspension by the Owner for Convenience. 11.3.1 § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work Work, in whole or in part for such period of time as the Owner may determine.
11.3.2 § 14.3.2 The Contract Price Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay delay, or interruption as described in Paragraph 11.
3.1under Section 14.3.1. Adjustment of the Contract Price Sum shall include profit. No adjustment shall be made to the extent:
11.3.2.1 extent .1 that performance is, was was, or would have been been, so suspended, delayed delayed, or interrupted interrupted, by another cause for which the Contractor is responsible; or
11.3.2.2 or .2 that an equitable adjustment is made or denied under another provision of the AgreementContract.
Appears in 7 contracts
Samples: Construction Contract, Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor
Suspension by the Owner for Convenience. 11.3.1 13.2.3.1 The Owner may, with or without causecause or prior notice, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
11.3.2 13.2.3.2 The Contract Price Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Paragraph 11Section 13.2.
3.1. Adjustment of the Contract Price shall include profit. No adjustment shall be made to the extent:
11.3.2.1 i. that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or
11.3.2.2 ii. that an equitable adjustment is made or denied under another provision of the AgreementContract.
Appears in 1 contract
Samples: Engineering, Procurement, and Construction Agreement
Suspension by the Owner for Convenience. 11.3.1 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
11.3.2 The Contract Price and Contract Time 14.3.2 An adjustment shall be adjusted made for increases in the cost and time of performance of the Contract, including profit on the increased cost of performance, caused by suspension, delay or interruption as described in Paragraph 11.
3.1. Adjustment of the Contract Price shall include profitinterruption. No adjustment shall be made to the extent:
11.3.2.1 : .1 that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or
11.3.2.2 or .2 that an equitable adjustment is made or denied under another provision of this Contract.
14.3.3 Adjustments made in the Agreementcost of performance may have a mutually agreed fixed or percentage fee.
Appears in 1 contract
Samples: Construction Contract (Monarch Casino & Resort Inc)