Suspension by the Owner for Convenience. § 13.2.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. § 13.2.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 13.2.
Appears in 15 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
Suspension by the Owner for Convenience. § 13.2.3.1 14.3.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work Work, in whole or in part for such period of time as the Owner may determine.
§ 13.2.3.2 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay delay, or interruption as described in under Section 13.214.3.1.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Construction Manager as Constructor, Standard Form of Agreement Between Owner and Architect
Suspension by the Owner for Convenience. § 13.2.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 13.2.3.2 The Contract Sum and Contract Time shall be adjusted for increases changes in the cost and time caused by suspension, delay or interruption as described in Section 13.2.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Suspension by the Owner for Convenience. § 13.2.3.1 14.2.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work Work, in whole or in part for such period of time as the Owner may determine.
§ 13.2.3.2 14.2.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay delay, or interruption as described in under Section 13.214.2.1.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Contractor
Suspension by the Owner for Convenience. § 13.2.3.1 14.3.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work Work, in whole or in part for such period of time as the Owner may determine.
§ 13.2.3.2 14.3.2 The Contract Sum and Contract Time shall may be adjusted for increases in the cost and time caused by suspension, delay delay, or interruption as described in under Section 13.2.14.3.1. Adjustment of the Contract Sum shall include profit. may include Fee. No adjustment shall be made to the extent
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Construction Manager as Constructor
Suspension by the Owner for Convenience. § 13.2.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 13.2.3.2 The 3.1. Adjustment of the Contract Sum and Contract Time shall include profit. No adjustment shall be adjusted for increases in made to the cost and time caused by suspension, delay or interruption as described in Section 13.2.extent
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Suspension by the Owner for Convenience. § 13.2.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 13.2.3.2 The Contract Sum and Contract Time shall may be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 13.2.13.2.3.1
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder