Common use of Suspension by the Owner for Convenience Clause in Contracts

Suspension by the Owner for Convenience. A. 14.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

AutoNDA by SimpleDocs

Suspension by the Owner for Convenience. A. 14.3.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.

Appears in 2 contracts

Samples: General Conditions of the Contract for Construction, Standard Form of Agreement Between Owner and Contractor (Corixa Corp)

Suspension by the Owner for Convenience. A. 14.3.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay delay, or interrupt the Work in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: Contract for Construction

Suspension by the Owner for Convenience. A. 14.3.1 A.14.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such a period of time as the Owner may determine.

Appears in 1 contract

Samples: Design Build Agreement

Suspension by the Owner for Convenience. A. § 14.3.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 The

Appears in 1 contract

Samples: Project Manual

Suspension by the Owner for Convenience. A. 14.3.1 The Owner may, without cause, in its discretion, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Contractor

Suspension by the Owner for Convenience. A. 14.3.1 3.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.detetmine. §

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Contractor (STAMPS.COM Inc)

AutoNDA by SimpleDocs

Suspension by the Owner for Convenience. A. 14.3.1 A.14.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Design Builder

Suspension by the Owner for Convenience. A. 14.3.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: Lease Agreement (Immunicon Corp)

Suspension by the Owner for Convenience. A. 14.3.1 The Owner may, without cause, order the Design-Builder Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine, subject to the Contractor's termination rights under Subparagraph 14.1.1.

Appears in 1 contract

Samples: Standard Form of Agreement (Windsor Woodmont Black Hawk Resort Corp)