Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1.
Appears in 4 contracts
Samples: Standard Form of Agreement Between Owner and Contractor, Construction Contract, Standard Form of Agreement Between Owner and Contractor
Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1Article 14.3.
Appears in 1 contract
Samples: Lump Sum Construction Agreement
Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or or; interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1Subparagraph 14.
Appears in 1 contract
Suspension by the Owner for Convenience. § 14.3.1 20.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 14.3.2 20.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.120.3.
1. No adjustment shall be made to the extent:
Appears in 1 contract
Samples: Standard Abbreviated Form of Agreement Between Owner and Contractor
Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt suspend the Work in whole or in part for such period of time as the Owner may determine.
§ 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost Contractor’s actual costs and for the time caused by of suspension, delay or interruption as described in Section 14.3.1.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Contractor (Adicet Bio, Inc.)
Suspension by the Owner for Convenience. § 14.3.1 A.14.3.1 The Owner may, without cause, order the Contractor Design-Builder in writing to suspend, delay delay, or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 14.3.2 A.14.3.2 The Contract Sum and the Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1A.14.
Appears in 1 contract