Common use of Suspension by the Owner for Convenience Clause in Contracts

Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1.

Appears in 4 contracts

Samples: Standard Form of Agreement Between Owner and Contractor, Construction Contract, Standard Form of Agreement Between Owner and Contractor

AutoNDA by SimpleDocs

Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1Article 14.3.

Appears in 1 contract

Samples: Lump Sum Construction Agreement

Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or or; interrupt the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1Subparagraph 14.

Appears in 1 contract

Samples: Construction Contract (Empire Resorts Inc)

Suspension by the Owner for Convenience. § 14.3.1 20.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 20.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.120.3. 1. No adjustment shall be made to the extent:

Appears in 1 contract

Samples: Standard Abbreviated Form of Agreement Between Owner and Contractor

AutoNDA by SimpleDocs

Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt suspend the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost Contractor’s actual costs and for the time caused by of suspension, delay or interruption as described in Section 14.3.1.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Contractor (Adicet Bio, Inc.)

Suspension by the Owner for Convenience. § 14.3.1 A.14.3.1 The Owner may, without cause, order the Contractor Design-Builder in writing to suspend, delay delay, or interrupt the Work in whole or in part for such period of time as the Owner may determine. § 14.3.2 A.14.3.2 The Contract Sum and the Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1A.14.

Appears in 1 contract

Samples: Design Build Agreement (Badger State Ethanol LLC)