Synchronisation Commissioning and Commercial Operation. 8.1 The Developer shall provide at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System. 8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 8.3 The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System. 8.4 The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 8.5 The Developer shall commission the Project within 12 (twelve)/24 (twenty four)13 months from the Effective Date.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 8.1. The Developer shall provide at least sixty forty (6040) days advanced preliminary written notice and at least thirty twenty (3020) days advanced final written notice to ESCOM BESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 8.2. Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 8.3. The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-sub- station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 8.4. The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 8.5. The Developer shall commission the Project within 12 18 (twelve)/24 (twenty four)13 eighteen) months from the Effective DateDate as per PPA from the date of concurrence from KERC.
Appears in 2 contracts
Synchronisation Commissioning and Commercial Operation. 8.1 The Developer shall provide at least sixty forty (6040) days advanced preliminary written notice and at least thirty twenty (3020) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 The Developer shall commission the Project within 12 18 (twelve)/24 eighteen)/30 (twenty four)13 thirty)14 months from the Effective Date.
Appears in 1 contract
Samples: Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 8.1. The Developer shall provide at least sixty forty (6040) days advanced preliminary written notice and at least thirty twenty (3020) days advanced final written notice to ESCOM BESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 8.2. Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 8.3. The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 8.4. The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 8.5. The Developer shall commission the Project within 12 18 (twelve)/24 (twenty four)13 eighteen) months from the Effective DateDate as per PPA from the date of concurrence from KERC.
Appears in 1 contract
Samples: Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 The Developer shall provide at least sixty forty (6040) days advanced preliminary written notice and at least thirty twenty (3020) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 The Developer shall commission the Project within 12 (twelve)/24 Twelve) months from the Effective Date. The Developer shall commission the Project within 18 (twenty four)13 eighteen) months from the Effective Date.
Appears in 1 contract
Samples: Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 β
8.1. The Developer shall provide at least sixty forty (6040) days advanced preliminary written notice and at least thirty twenty (3020) days advanced final written notice to ESCOM BESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 8.2. Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 8.3. The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 8.4. The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 8.5. The Developer shall commission the Project within 12 18 (twelve)/24 (twenty four)13 eighteen) months from the Effective DateDate as per PPA from the date of concurrence from KERC.
Appears in 1 contract
Samples: Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 The Developer shall provide at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 The Developer shall commission the Project within 12 18 (twelve)/24 eighteen)/30 (twenty four)13 thirty)13 months from the Effective Date.
Appears in 1 contract
Samples: Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 The Developer shall provide at least sixty forty (6040) days advanced preliminary written notice and at least thirty twenty (3020) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-sub- station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 The Developer shall commission the Project within 12 18 (twelve)/24 (twenty four)13 eighteen) months from the Effective DateDate as per PPA from the date of concurrence from KERC.
Appears in 1 contract
Samples: Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 The Developer shall provide at least sixty forty (6040) days advanced preliminary written notice and at least thirty twenty (3020) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 The Developer shall commission the Project within 12 18 (twelve)/24 (twenty four)13 eighteen) months from the Effective Date.
Appears in 1 contract
Samples: Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 8.1. The Developer shall provide at least sixty forty (6040) days advanced preliminary written notice and at least thirty twenty (3020) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 8.2. Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 8.3. The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-sub- station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 8.4. The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 8.5. The Developer shall commission the Project within 12 18 (twelve)/24 (twenty four)13 eighteen) months from the Effective DateDate as per PPA from the date of concurrence from KERC.
Appears in 1 contract
Samples: Power Purchase Agreement