Toe Wall Sample Clauses

Toe Wall. Sr. No. Chainage (Km) Design Length ( Km TCS Code Remarks From To (1) (2) (3) (4) (5) (6) 1 1.750 1.800 0.050 TCS-4 One side 2 1.800 1.900 0.100 TCS-3 Both Sides 3 2.075 2.100 0.025 TCS-4 One side 4 4.200 4.275 0.075 TCS-3 Both Sides 5 4.350 4.425 0.075 TCS-4 One side 6 4.600 4.725 0.125 TCS-3 Both Sides 7 4.825 5.000 0.175 TCS-4 One side 8 5.075 5.175 0.100 TCS-4 One side 9 5.475 5.650 0.175 TCS-3 Both Sides 10 5.775 5.875 0.100 TCS-4 One side 11 6.600 6.825 0.225 TCS-4 One side 12 6.925 6.975 0.050 TCS-4 One side 13 7.225 7.250 0.025 TCS-4 One side 14 7.250 7.370 0.120 TCS-3 Both Sides 15 7.380 7.525 0.145 TCS-3 Both Sides 16 7.525 7.600 0.075 TCS-4 One side 17 7.700 7.800 0.100 TCS-4 One side 18 9.100 9.150 0.050 TCS-4 One side 19 9.200 9.250 0.050 TCS-4 One side 20 9.400 9.450 0.050 TCS-3 Both Sides 21 9.575 9.650 0.075 TCS-4 One side 22 10.600 10.790 0.190 TCS-4 One side 23 10.810 10.950 0.140 TCS-4 One side 24 11.225 11.325 0.100 TCS-4 One side 25 11.550 11.600 0.050 TCS-3 Both Sides 26 11.850 11.956 0.106 TCS-4 One side 27 11.970 12.325 0.355 TCS-4 One side 28 12.875 13.625 0.750 TCS-4 One side 29 15.800 15.828 0.028 TCS-4 One side 30 15.846 16.125 0.279 TCS-4 One side 31 16.125 16.275 0.150 TCS-4 One side 32 16.275 16.650 0.375 TCS-4 One side Sr. No. Chainage (Km) Design Length ( Km TCS Code Remarks (1) (2) (3) (4) (5) (6) 33 17.025 17.100 0.075 TCS-4 One side 34 17.275 17.325 0.050 TCS-4 One side 35 18.025 18.100 0.075 TCS-4 One side 36 18.150 18.225 0.075 TCS-4 One side 37 18.225 18.250 0.025 TCS-3 Both Sides 38 18.280 18.450 0.170 TCS-3 Both Sides 39 19.750 19.795 0.045 TCS-4 One side 40 19.805 20.075 0.270 TCS-4 One side 41 20.600 20.675 0.075 TCS-4 One side 42 20.675 20.800 0.125 TCS-4 One side 43 20.800 20.850 0.050 TCS-4 One side 44 20.975 21.200 0.225 TCS-4 One side Total Length in Km. = 5.748
AutoNDA by SimpleDocs
Toe Wall. Toe Wall shall be provided as per the requirement of site conditions to restrict the right of way; however minimum 1400 m length shall be provided. Reinforced Earth Wall: Reinforced Earth Wall shall be provided as per the requirement of site conditions; however minimum 1780 m length shall be provided between Main carriageway and Slip Road/Ramp. Embankment Protection: High embankment slop protection shall be provided as per the requirement of the site as per manual, however minimum 9300.00 cum stone boulder pitching shall be provided in the embankment slop. Note:

Related to Toe Wall

  • Sprinkler System If there now is or shall be installed in said building a "sprinkler system" the Tenant agrees to keep the appliances thereto in the demised premises in repair and good working condition, and if the New York Board of Fire Underwriters or the New York Fire Insurance Exchange or any bureau, department or official of the State or local government requires or recommends that any changes, modifications, alterations or additional sprinkler heads or other equipment be made or supplied by reason of the Tenant's business, or the location of partitions, trade fixtures, or other contents of the demised premises, or if such changes, modifications, alterations, additional sprinkler heads or other equipment in the demised premises are necessary to prevent the imposition of a penalty or charge against the full allowance for a sprinkler system in the fire insurance rate as fixed by said Exchange or by any fire insurance company, the Tenant will at the Tenant's own expense, promptly make and supply such changes, modifications, alterations, additional sprinkler head or other equipment. As additional rent hereunder the Tenant will pay to the Landlord, annually in advance, throughout the term 100%, toward the contract price for sprinkler supervisory service.

  • Ceiling Company and its subcontractors will not affix, attach, or suspend any lighting fixtures, signs, or other fixtures or devices of any kind or nature from the ceiling above any of the Premises without the prior written approval of Authority.

  • Apprentice Wages (a) Apprentices’ rates of pay are set out in Appendix B which includes the description of the calculations.

  • NOISE/WASTE The Tenant agrees not to commit waste on the premises, maintain, or permit to be maintained, a nuisance thereon, or use, or permit the premises to be used, in an unlawful manner. The Tenant further agrees to abide by any and all local, county, and State noise ordinances.

  • System Logging The system must maintain an automated audit trail which can 20 identify the user or system process which initiates a request for PHI COUNTY discloses to 21 CONTRACTOR or CONTRACTOR creates, receives, maintains, or transmits on behalf of COUNTY, 22 or which alters such PHI. The audit trail must be date and time stamped, must log both successful and 23 failed accesses, must be read only, and must be restricted to authorized users. If such PHI is stored in a 24 database, database logging functionality must be enabled. Audit trail data must be archived for at least 3 25 years after occurrence.

  • Common Areas - Rules and Regulations Lessor or such other person(s) as Lessor may appoint shall have the exclusive control and management of the Common Areas and shall have the right, from time to time, to establish, modify, amend and enforce reasonable rules and regulations (“Rules and Regulations”) for the management, safety, care, and cleanliness of the grounds, the parking and unloading of vehicles and the preservation of good order, as well as for the convenience of other occupants or tenants of the Building and the Project and their invitees. Lessee agrees to abide by and conform to all such Rules and Regulations, and to cause its employees, suppliers, shippers, customers, contractors and invitees to so abide and conform. Lessor shall not be responsible to Lessee for the non-compliance with said Rules and Regulations by other tenants of the Project.

  • Apprentice Employment and

  • APPRENTICES 6.36.1 The Contractor acknowledges and agrees that, if this Contract involves a dollar amount greater than or a number of working days greater than that specified in Labor Code Section 1777.5, this Contract is governed by the provisions of Labor Code Section 1777.5. It shall be the responsibility of the Contractor to ensure compliance with this Article and with Labor Code Section 1777.5 for all apprenticeable occupations. 6.36.2 Pursuant to Labor Code Section 1777.5 if that Section applies to this Contract as indicated above, the Contractor and any subcontractors under him employing workers in any apprenticeable craft or trade in performing any work under this Contract shall apply to the applicable joint apprenticeship committee for a certificate approving the Contractor or subcontractor under the applicable apprenticeship standards and fixing the ratio of apprentices to journeymen employed in performing the work. 6.36.3 Pursuant to Labor Code Section 1777.5 if that Section applies to this Contract as indicated above, he Contractor and any subcontractor under him may be required to make contributions to the apprenticeship program. 6.36.4 The Contractor and all subcontractors under him shall comply with Labor Code Section 1777.6 which Section forbids certain discriminatory practices in the employment of apprentices.

  • Outputs Analogue and digital outputs of protected content are allowed if they meet the requirements in this section and if they are not forbidden elsewhere in this Agreement..

  • System Upgrades The Connecting Transmission Owner shall procure, construct, install, and own the System Upgrade Facilities and System Deliverability Upgrades described in Attachment 6 of this Agreement. To the extent that design work is necessary in addition to that already accomplished in the Class Year Interconnection Facilities Study for the Interconnection Customer, the Connecting Transmission Owner shall perform or cause to be performed such work. If all the Parties agree, the Interconnection Customer may construct System Upgrade Facilities and System Deliverability Upgrades. 5.2.1 As described in Section 32.3.5.3 of the SGIP in Attachment Z of the ISO OATT, the responsibility of the Interconnection Customer for the cost of the System Upgrade Facilities and System Deliverability Upgrades described in Attachment 6 of this Agreement shall be determined in accordance with Attachment S of the ISO OATT, as required by Section 32.3.5.3.2