Examples of APPROVED AS NOTED in a sentence
The approval or disapproval of submittals by the Reviewer shall be indicated by one of the following designations: "APPROVED" (no further action required), "APPROVED AS NOTED" (make corrections noted - no further submittal required), "RESUBMIT" (make corrections noted and resubmit for approval), or "NOT APPROVED" (rejected - do not resubmit the concept or component as submitted).
The approval or disapproval of submittals by the Reviewer must be indicated by one of the following designations: "APPROVED" (no further action required), "APPROVED AS NOTED" (make corrections noted - no further submittal required), "RESUBMIT" (make corrections noted and resubmit for approval), or "NOT APPROVED" (rejected - do not resubmit the concept or component as submitted).
Only shop drawings that have been "APPROVED", or "APPROVED AS NOTED" must be submitted to the Department for review.
B - SUBMITTAL APPROVED AS NOTED (RESUBMIT): Signifies Equipment and Material represented by the Submittal conforms with the design concept and complies with the intent of the Contract Documents and is approved for incorporation in the Work in accordance with Engineer's notations.
B - SUBMITTAL APPROVED AS NOTED (RESUBMIT) Signifies Equipment or Material represented by the Submittal conforms to the design concept and complies with the intent of the Contract and is approved for incorporation in the Work in accordance with Engineer's notations.
B - SUBMITTAL APPROVED AS NOTED (RESUBMIT) Signifies Equipment or Material represented by the Submittal conforms to the design concept and complies with the intent of the Contract Documents and is approved for incorporation in the Work in accordance with Engineer's notations.
B - SUBMITTAL APPROVED AS NOTED (RESUBMIT) Signifies Equipment or Material represented by the Submittal conforms with the design concept and complies with the intent of the Contract Documents and is approved for incorporation in the Work in accordance with Owner's notations.
Work may proceed when submittals have been returned marked APPROVED or APPROVED AS NOTED, provided the Work is performed in accordance with Engineer’s notations.
B - SUBMITTAL APPROVED AS NOTED (RESUBMIT) Signifies Equipment or Material represented by the Submittal conforms with the design concept and complies with the intent of the Contract Documents and is approved for incorporation in the Work in accordance with Engineer's notations.
Within twenty one (21) calendar days after receipt of the submittals, two (2) copies of each submittal will be returned to the Contractor by the Government marked either "APPROVED", "APPROVED AS NOTED" or "DISAPPROVED".