Capital Cost Estimate definition

Capital Cost Estimate means an estimate of the cost to implement the Capital Project inclusive of Project Development through completion of Construction that accounts for risk to the cost elements and the schedule to complete the project.
Capital Cost Estimate means the estimate by the Corporation of the Capital Cost as set out in Appendix 3.
Capital Cost Estimate means an estimate(s) of probable costs with variances of plus/minus 25%. The estimate(s) will also be noted in today’s dollars (no allowance for inflation). This is a typical industry standard when budgeting from conceptual design drawings. The estimates of actual construction value are refined as the Project goes through the detailed design phase.

Examples of Capital Cost Estimate in a sentence

  • Table 1-4: Capital Cost Estimate Summary In addition to the above, the total life of mine sustaining capital is estimated to be $361.7 million.

  • Phase 1 Capital Cost Estimate Process plant Mining (pre-production costs) Power infrastructure Buildings, offices and accommodation TSF, WRD, ROM, water supply, civil works CSR, owners team, G&A EPCM Sub total Contingency & estimating inaccuracies Total The incremental capital cost of the mine, process plant and associated infrastructure for Phase 2 is estimated at US$270 million.

  • The JPB had expected to re-baseline its Capital Cost Estimate in mid-2019 after it had assessed the cost and schedule impacts to the Electrification contract, had issued the CEMOF Modification contract, the last major construction contract, and completed its Monte Carlo risk assessment update to inform the contingency requirements.

  • Contingency provides an allowance to the Capital Cost Estimate for undeveloped details within the Scope of Work covered by the estimate.

  • Phase 1 Capital Cost Estimate The incremental capital cost of the mine, process plant and associated infrastructure for Phase 2 is estimated at US$270 million.

  • A breakdown of the key capital cost areas is shown in table 9 below.Table 9 – Josemaria Capital Cost Estimate Initial Capital Costs Sustaining capital for Josemaria has been estimated based on maintaining the operation at full production for the entire 19-year mine life without the expectation of any significant expansion in the process plant capacity or replacement of any significant components of fixed infrastructure.

  • WBS Costs (AUD $) DIRECT COSTS 10000Mine2,870,28120000Crushing Plant and Materials Handling2,047,87930000Product Transport and Logistics1,805,49240000Port226,64650000Infrastructure and Head Works3,899,62760000Road Use Levy450,000 INDIRECT COSTS 70000Owner’s Costs2,523,90680000EPCM1,897,717 TOTAL15,721,547 ⯈ Operating Cost EstimateTable 3 – Capital Cost Estimate SummaryThe operating cost estimate for the Project (FOB basis) is presented at a summary level in Table 4.

  • A summary of the capital cost is included in Table 1.2. Table 1.2 Summary of Capital Cost Estimate The capital cost estimate was prepared by Quest and Micon, primarily based on factorization of existing cost estimates (completed by AECOM, Hatch and SLR for Quest’s 2013 PFS) to reflect the updated project scope.

  • Regarding capital costs, the Department will require each project sponsor to complete an Operating Data Sheet similar to the example shown in Attachment 4, and a Capital Cost Estimate sheet similar to the example shown in Attachment 5.

  • SERVICEESTIMATES OF EXISTING OPERATIONSEXISTING FUNDING SUMMARYALTERNATIVE FUNDING SCENARIOS Subsidy Estimate (Operating Cost - Fare Revenue) Capital Cost Estimate useful for a summary comparison.

Related to Capital Cost Estimate

  • Capital Cost means costs incurred or proposed to be incurred by the municipality or a local board thereof directly or by others on behalf of, and as authorized by, the municipality or local board,

  • Cost Estimate means the detailed projected expenditure, including material costs and overhead, equipment costs and overhead, labor costs and overhead, and all taxes associated with each major material and service component, required for a line extension. It shall also separately identify any incremental costs associated with providing premium services. The Company may, for the purpose of standardization, establish standard construction cost estimates, for basic or premium service plans, which shall not exceed, in any event, the average cost of constructing such line extensions in the area involved, in which case the term “cost estimate” as used in this section will be understood to mean the standard estimate thus established.

  • Capital Costs means an add-on to the blended base amount, which shall compensate for Medicaid’s portion of capital costs. Capital costs for buildings, fixtures and movable equipment are defined in the hospital’s base year cost report, are case-mix adjusted, are adjusted to reflect 80 percent of allowable costs, and are adjusted to be no greater than one standard deviation off the mean Medicaid blended capital rate.

  • Estimated Working Capital Adjustment means the amount by which the Estimated Working Capital is greater or less than the Base Working Capital, any such excess amount being treated as a positive number and any shortfall being treated as a negative number;

  • Estimated Working Capital has the meaning set forth in Section 2.3(a).

  • Estimate means to be based on technical evaluation of the sources contributing to the discharge including, but not limited to, pump capabilities, water meters, and batch discharge volumes.

  • Estimated Project Cost means Benchmark cost of MNRE which is Rs 8.00 Crore/MWp as per MNRE letter no. 03/20/2014-15/GCRT/11.12.14 at the time of Bid Due date.

  • Estimated Value means the value of the Contract estimated under these Contract and Procurement Regulations.

  • Operating Cost means the costs associated with operating a multifamily development once the project is placed in service.

  • Fixed capital cost means the capital needed to provide all the depreciable components.

  • Estimated Net Working Capital has the meaning set forth in Section 2.3(a).

  • Net Working Capital Adjustment means (a) the amount by which Net Working Capital as of immediately prior to the Closing exceeds Target Net Working Capital or (b) the amount by which Net Working Capital as of immediately prior to the Closing is less than Target Net Working Capital, in each case, if applicable; provided, that any amount which is calculated pursuant to clause (b) above shall be deemed to be a negative number.

  • SF1-4 Intrinsic Loss Estimate means total losses under this Single Family Shared-Loss Agreement in the amount of eleven million dollars ($11,000,000.00).

  • Base Working Capital means $25,000,000.

  • Operating Costs means the incremental expenses incurred by the Recipient on account of Project implementation, management, and monitoring, including for office space rental, utilities, and supplies, bank charges, communications, vehicle operation, maintenance, and insurance, building and equipment maintenance, advertising expenses, travel and supervision, salaries of contractual and temporary staff, but excluding salaries, fees, honoraria, and bonuses of members of the Recipient’s civil service.

  • Consolidated Working Capital Adjustment means, for any period of determination on a consolidated basis, the amount (which may be a negative number) by which Consolidated Working Capital as of the beginning of such period exceeds (or is less than) Consolidated Working Capital as of the end of such period.

  • Direct Cost means a cost not to exceed the cost of labor, material, travel and other expenditures to the extent the costs are directly incurred to provide the relevant assistance or service. “Direct Cost” to the Acquirer for its use of any of a Respondent’s employees’ labor shall not exceed the average hourly wage rate for such employee;

  • Capital Charge means the deemed opportunity cost of employing Capital in the Company’s businesses, determined as follows: Capital Charge = Capital X Cost of Capital

  • Agreed Value of any Contributed Property means the fair market value of such property or other consideration at the time of contribution as determined by the General Partner. The General Partner shall use such method as it determines to be appropriate to allocate the aggregate Agreed Value of Contributed Properties contributed to the Partnership in a single or integrated transaction among each separate property on a basis proportional to the fair market value of each Contributed Property.

  • Project Cost means the price payable to Service Provider over the entire period of Agreement (i.e. Rs. <in words>) for the full and proper performance of its contractual obligations.

  • Working Capital Adjustment has the meaning set forth in Section 2.5(a).

  • Net Working Capital Adjustment Amount means an amount (which may be a positive or negative number) equal to (a) the Closing Date Net Working Capital minus (b) the Target Net Working Capital.

  • Net Working Capital Amount means, with respect to a Participating McNeil Partnership, the excess of the Positive Excess Cash Balance of such Participating McNeil Partnership over the cash on hand of such Participating McNeil Partnership immediately prior to the Effective Time.

  • Cost price means the actual cost of an item or article of tangible personal property computed in the

  • Target Working Capital Amount means $75,000,000.

  • Intrinsic Loss Estimate means total losses under the shared loss agreements in the amount of One hundred Sixty-eight million dollars ($168,000,000.00).