Examples of Commissioning Completion Date in a sentence
From the Commissioning Completion Date for the first Wind Turbine and through the end of the Term, Supplier shall maintain or cause to be maintained Excess Liability Insurance of not less than Five Million Dollars (U.S. $5,000,000).
From the Commissioning Completion Date for the first Wind Turbine and through the end of the Term, Buyer shall maintain or cause to be maintained Excess Liability Insurance of not less than Five Million Dollars (U.S. $5,000,000).
From the Commissioning Completion Date for the first Wind Turbine and through the end of the Term, Buyer shall maintain or cause to be maintained All Risk Property Insurance (including earth movement and flood, collapse, sinkhole and subsidence) on a completed value form.
Concurrently with the Project Substantial Completion, all WTG Commissioning Delay Liquidated Damages shall be due and payable and payment of such liquidated damages shall constitute the sole liability of Seller and the exclusive remedy of the Owner for Seller's failure to meet the Guaranteed WTG Commissioning Completion Date.
In the event of occurrence of suspension of the Wind Turbine Work by Seller pursuant to Section 6.2, Seller shall be entitled to a Change Order reflecting the result and impact of such suspension on the Wind Turbine Work, including, but not limited to, Contract Price, the Delivery Schedule, the Warranty and the Guaranteed WTG Commissioning Completion Date.
During the period from the Commencement Date for the first Wind Turbine until the Final Commissioning Completion Date, Buyer shall pay Supplier a fee equal to One Hundred Fifty-Seven Dollars ($157) per day per Wind Turbine that has achieved Commissioning Completion during such period (the “Interim Service Fee”).
Seller shall complete Commissioning of each WTG no later than its respective Guaranteed WTG Commissioning Completion Date.
If Commissioning of WTGs is not achieved by the Guaranteed WTG Commissioning Completion Date calculated by the sum of the actual completion days for Commissioning of all WTGs divided by the number of WTGs with the consideration of Excusable Delay applicable herein, Seller shall pay as liquidated damages to Buyer an amount equal to *** US Dollars (US $***) per WTG ("WTG Commissioning Delay Liquidated Damages") for each day multiplied by the number of WTGs.
Although EGAT shall by Law and the provisions of Section 2.6 and this Section 2.8.1 have legal title to the New Transmission Facilities from the start of their construction, the Generator shall bear the risk of loss of or damage to the New Transmission Facilities until the NTF Commissioning Completion Date.
On and after the date that is nine (9) months after the Commissioning Completion Date of the last Nominated Wind Turbine, Buyer shall no longer have the right to request a verification of the Power Curve.