Completion Date 1 definition

Completion Date 1 means the fifth Business Day following the day when the last of the Conditions Precedent 1 has been satisfied or waived, in accordance with this Agreement or at such other time as may be agreed in writing between QIWI and the Investor;
Completion Date 1 means the date on which an acceptance of a Completion Certificate is issued by Falkirk Council’s Building Standards Unit relative to the nth Unit in respect of which an acceptance of a Completion Certificate is so issued where “n” is a number equal to 34% of the number of Units the building of which is permitted in terms of the Further Planning Permission to which it relates and where “n” is a whole number or is rounded up to the nearest whole number;

Examples of Completion Date 1 in a sentence

  • For example, if a Contractor requests time adjustments of 10 days to Intermediate Completion Date 1, 15 days to Intermediate Completion Date 2, 15 days to Intermediate Completion Date 3, and 15 days to the Contract Completion Date, the magnitude of the time extension request is 15 days.

  • For example, if a contractor requests time adjustments of 10 days to Intermediate Completion Date 1, 15 days to Intermediate Completion Date 2, 15 days to Intermediate Completion Date 3, and 15 days to the Contract Completion Date, the magnitude of the time extension request is 15 days.

  • Within 30 (thirty) calendar days after the Completion Date 1 QIWI shall execute and deliver (or procure the execution and delivery of) share certificate in respect of the Subscription Shares 1 to the Investor.

  • Competency/Objective Instructional Plan/Assignments Methods of Assessment Projected Completion Date 1.

  • Measures: % of actual (all funds) expended to adopted budget and % of actual revenues collected to adopted budget Expected Completion Date: 1.

  • RecommendationFrom narrative starting on page 12 SCTA ActionEstimated Initiation DateEstimated Completion Date 1.

  • No.OIG RecommendationAction Official(s)Proposed Corrective ActionProposed Completion Date 1.

  • Contractor/Service Provider shall perform the following tasks: Task Description Deliverables Completion Date 1 Provide Chula Vista Food Bank partners with food/supplies to meet the increased demand.

  • Name of Contract Value of Outstanding work (Equivalent Pak Rs. Millions) Estimated Completion Date 1.

  • Anticipated Completion Date: 1) Training will be provided on an ongoing basis and will start June 2016 and continue through May 2017.

Related to Completion Date 1

  • Final Completion Date means the date on which Final Completion occurs.

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • Target Completion Date has the meaning given such term in Section 3.3(b).

  • Construction Completion Date means date of the completion of the Construction Period, which shall be at the expiry of a period of 24 (Twenty Four) months from the Compliance Date or such other date (with the consent of the Authority) by which the overall development of the Project is completed in accordance with the provisions of this Concession Agreement and when the Construction Completion Certificate is issued by Authority as per Article 14.1.

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • Substantial Completion Date means the required date for Substantial Completion of the Project. The Substantial Completion Date can be adjusted only by written Change Order.

  • Scheduled Completion Date shall be the date set forth in Clause 10.3;

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • Commercial Operation Date (COD) means the date certified by the DISCOM’s committee upon successful commissioning (as per provisions of the PPA) of the project when all equipments as per rated capacity have been installed and energy has flown into the grid.

  • Completion Period means the period starting from the date of issue of "Order" and required to complete the work in all respect.

  • project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;

  • Completion Schedule means the fulfilment of the Related Services by the Supplier in accordance with the terms and conditions set forth in the Contract;

  • COMPLETION TIME means the period by ‘date/month’ specified in the ‘Letter of Intent/Award’ or date mutually agreed upon for handing over of the intended scope of work, the erected equipment/plant which are found acceptable by the Engineer, being of required standard and conforming to the specifications of the Contract.

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • Final Completion Certificate has the meaning set forth in Section 11.6.

  • Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

  • Construction Completion Certificate means the certificate issued under ARTICLE 14.

  • Completion Deadline means the date by which the Arrangement is to be completed, which date shall be April 30, 2014 or such later date as may be agreed to in writing by the Parties;

  • Phase 1 means the phase of the ATP comprised of: (1) improvements to the State Street Substation; (2) construction of the Proposed Line; (3) the rebuilding of NYSEG’s existing Lines 971 and 000 xxxxx xx Xxxxxxxx Xxxx xx the NYSEG ROW to allow for construction of the Proposed Line as intended; (4) improvements to the Elbridge Substation to accept the Proposed Line; and (5) National Grid’s conveyance to NYSEG of the NYSEG Acquired ROW and such other land interests as contemplated by the Purchase and Sale Agreement.

  • Construction Schedule means a construction schedule indicating the planned start and completion dates of the major activities of the Work as set out in Appendix [ ], a future Appendix;

  • Completion Payment means the payment for the 20% of the Charges for each Apprenticeship that under the ESFA Rules is only paid once an Apprentice takes their end point assessment, including as the case may be Apprenticeships funded by Transferred Levy Funds;

  • Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.

  • Final Acceptance Date means the date on which Final Acceptance occurs.

  • Construction Period means the period commencing from the Appointed Date and ending on the date of the Completion Certificate;

  • Substantial Completion Certificate means the certificate issued and approved by the Authority indicating the date upon which the Trade Contractor Work (or a designated portion thereof) is Substantially Complete.