Examples of Completion of Facilities in a sentence
Effective Date for Determining Time for Completion3.1 Effective Date (Reference GCC Clause 1) The Time of Completion of Facilities shall be determined from the date of the Notification of Award i.e., from………………… Article 4.
The aforesaid retained amount shall be paid along with payment due on completion of Trial Operation / Completion of Facilities.
The procedure tends to be a matter of local protocol at Councils and has not tended to be subject to scrutiny.
Time for CompletionThe Time of Completion of Facilities shall be determined in Months from the date of the Letter of Award (LoA) i.e., w.e.f. XX.XX.XXXX.
Effective Date for Determining Time for Completion 3.1 Effective Date (Reference GCC Clause 1) The Time of Completion of Facilities shall be determined from the date of the Notification of Award i.e., from ………………… Article 4.
If the successful Completion of Facilities is not attained within 18 months from the date of Notification of Award by NLCIL on BHEL, for reasons attributable to Associate, then the Liquidated Damages payable at the rate of 0.5% per week of delay or part thereof of supply and services subject to a ceiling of 10% of the total value of contract for supply & services, shall be payable by Associate on whom BHEL has placed order for BESS.17.
It will be the responsibility of the Contractor to provide all commissioning spares including consumable spares required for initial operation till the Completion of Facilities.
The Construction Completion Schedule with associated construction values for each benchmark shall set forth completion dates for the following benchmarks as needed: i) Completion of Excavation; ii) Completion of Electrical; iii) Completion of Mechanical; iv) Completion of Facilities; v) Completion of Hardscaping and Landscaping; and any further construction benchmarks and conditions as may be determined by the Director of Public Works.
On 16.03.2016, PCTEL completed facilities Cooling Tower No. 3 (CT#3), Cooling Tower No. 4 (CT#4) and Control Room under Clause 24 of the General Conditions of Contract (GCC) (Commissioning and Completion of Facilities).
On 21.04.2016, PCTEL informed KBUNL that it had completed the works under Clause 24 of the GCC and requested issuance of a certificate of Completion of Facilities (‘COF’) and release of its dues.