CPM Network definition
Examples of CPM Network in a sentence
The Contractor shall also submit a Resource Charts, generated from the Contractor's CPM Network Diagram, showing the anticipated manpower and main Construction Equipment usage during the execution of the Project.
Charts The Contractor shall also submit a Resource Charts, generated from the Contractor's CPM Network Diagram, showing the anticipated manpower and main Construction Equipment usage during the execution of the Project.
The Contractor shall also submit a forecast Cumulative Physical Progress 'S' curve based on the time-phased distribution of cost in the CPM Network Logic Diagram, expressed in percentage terms.
The Contractor shall also Resource Charts, generated from the Contractor’s CPM Network Diagram, showing the anticipated manpower and main Construction Equipment usage during the execution of the Project.
This ‘S’ curve shall be generated from the computerised CPM Network Logic Diagram.
The program shall be in the form of a Critical Path Method Network (CPM Network) showing the order of procedure and a description of the construction methods and arrangements by which the Contractor proposes to carry out the works .It should also be supplemented by a time –bar chart of the same program.
CPM Network - The CPM Network is a transferable electronic copy of project software data and files.
This Time Bar-chart Schedule shall be submitted to the Engineer together with the CPM Network.
The program shall be in the form of a Critical Path Method Network (CPM Network) showing the order of procedure and a description of the construction methods and arrangements by which the Contractor proposes to carry out the works.
In preparing the CPM Network and the Time Bar-chart Schedule the Contractor shall make due allowances for possible delays.