Examples of Guaranteed Project Substantial Completion Date in a sentence
Except as set forth in Section 6.2, Section 9.2 or Section 3.4 of this Agreement or unless otherwise expressly provided by the terms of this Agreement, there shall be no increase in the Contract Price or extension in the Guaranteed Project Substantial Completion Date except as agreed in writing by the Parties or otherwise expressly provided by this Agreement.
The proposed recovery schedule will, at a minimum, demonstrate the means by which Seller intends to recapture lost time, meet Critical Milestones and achieve Project Substantial Completion by the Guaranteed Project Substantial Completion Date.
Seller agrees that if Project Substantial Completion is not achieved by the Guaranteed Project Substantial Completion Date, then Seller shall pay the Daily Delay Liquidated Damages to Purchaser for each Day that Seller fails to achieve Project Substantial Completion after the Guaranteed Project Substantial Completion Date until Project Substantial Completion is achieved (the “Delay Liquidated Damages”).
After Seller’s compliance with Section 10.2, the Parties shall execute a Change Order to (a) adjust the Critical Path Project Schedule (other than the Guaranteed Project Substantial Completion Date), to account for material delays to the Critical Path Project Schedule resulting from the Excusable Event and/or (b) adjust the Contract Price to account for the material increase in the cost of the performance of the Work resulting from the Excusable Event.
After achieving Project Substantial Completion, Seller may, at its option and sole cost and expense, continue to attempt to achieve the Minimum Guaranteed Plant Reliability until the date that is ninety (90) Days after the Guaranteed Project Substantial Completion Date (such period, the “Reliability Test Cure Period”).
After achieving Project Substantial Completion, Seller may, at its option and sole cost and expense, continue to attempt to achieve the Minimum Guaranteed Plant Capacity until the date that is ninety (90) Days after the Guaranteed Project Substantial Completion Date (such period, the “Capacity Test Cure Period”).
After achieving Project Substantial Completion, Seller may, at its option and sole cost and expense, continue to attempt to achieve the Guaranteed XXXX XX Efficiency until the date that is ninety (90) Days after the Guaranteed Project Substantial Completion Date (such period, the “XXXX XX Efficiency Test Cure Period”).
After achieving Project Substantial Completion, Seller may, at its option and sole cost and expense, continue to attempt to achieve the Guaranteed PV Plant Capacity and Guaranteed XXXX Storage Capacity until the date that is ninety (90) Days after the Guaranteed Project Substantial Completion Date (such period, the “Capacity Test Cure Period”).
After achieving Project Substantial Completion, Seller may, at its option and sole cost and expense, continue to attempt to achieve the Guaranteed PV Plant Capacity until the date that is ninety (90) Days after the Guaranteed Project Substantial Completion Date (such period, the “Capacity Test Cure Period”).
Developer shall cause Project Substantial Completion to occur on or before the Guaranteed Project Substantial Completion Date.