Examples of Mechanical Completion Date in a sentence
At least twenty-one (21) days, but no more than thirty-five (35) days, prior to the date on which Seller anticipates the Work will achieve Mechanical Completion (the “Anticipated Mechanical Completion Date”), Seller shall provide to Buyer written notice of the Anticipated Mechanical Completion Date.
If this Agreement is terminated prior to the Project Mechanical Completion Date, Contractor shall furnish Owner with any and all final documents which have been prepared, and the most up-to-date versions of documents which are not yet final.
Therefore, the Parties have agreed to quantify and to agree upon such damages in advance.3.3.3 In the event Contractor fails to achieve (a) Mechanical Completion by the Scheduled Mechanical Completion Date or (b) Construction Completion by the Scheduled Construction Completion Date, in either case, Contractor agrees to pay Covanta as liquidated damages (and not as a penalty nor subject to any proof of such loss)Contract art.
The relevant portions of Article 3.3 state:3.3.2 Contractor shall achieve Mechanical Completion no later than the Scheduled Mechanical Completion Date and Construction Completion no later than the Scheduled Construction Completion Date.
Contractor shall cause WTG Mechanical Completion with respect to each WTG to occur on or before the Guaranteed Mechanical Completion Date and otherwise in accordance with the requirements of this Agreement.