NEPA process completion definition

NEPA process completion means, with respect to the FHWA and the FTA, the point at which
NEPA process completion means, for the purposes of this part, with respect to FHWA or
NEPA process completion with respect to FHWA or FTA, means the point at which there is a specific action to do any of the following:

Examples of NEPA process completion in a sentence

  • Should the NEPA process result in a project with design concept and scope significantly different from that in the transportation plan or TIP, the project must meet the criteria in Chapter 8, Section 4(i)-(aa) for projects not from a TIP before NEPA process completion.

  • Conformity must be redetermined for any FHWA/FTA project if none of the following major steps has occurred within the most recent three-year period: NEPA process completion; start of final design; acquisition of a significant portion of the right-of-way; or approval of the plans, specifications and estimates.

  • Major steps in- clude NEPA process completion; start of final design; acquisition of a signifi- cant portion of the right-of-way; and, construction (including Federal ap- proval of plans, specifications and esti- mates).

  • Conformity must be redetermined for any FHWA/FTA project if three (3) years have elapsed since the most recent major step to advance the project (NEPA process completion; start of final design; acquisition of a significant por- tion of the right-of-way; or approval of the plans, specifications and estimates) occurred.

  • A major step is defined in today’s conformity rule as ‘‘* * * NEPA process completion; start of final design; acquisition of a significant portion of the right-of-way; and construction (including Federal approval of plans, specifications and estimates)’’ (40 CFR 93.104(d)).See EPA’s conformity website listed in Section I.B.2. to download an electronic copy of the June 30, 2003 proposal to this final rule and the latest EPA and DOT guidance implementing the court decision.

  • In accordance with 40 CFR 93.125(c), prior to making a project-level conformity determination for a transportation project, FHWA/FTA must obtain from the project sponsor and/or operator a written commitment, as defined in 40 CFR 93.101, to implement any project-level mitigation or control measure in the construction or operation of the project identified as a condition for NEPA process completion.

  • Conformity must be redetermined for any FHWA/FTA project if none of the following major steps has occurred within the past three years: NEPA process completion; start of final design; acquisition of a significant portion of the right-of-way; or approval of the plans, specifications and estimates.

  • Should the NEPA process result in a project with design concept and scope significantly different from that in the transportation plan or TIP, the project must meet the criteria in Sections 10 through 20 for projects not from a TIP before NEPA process completion.

  • Indeed, contrary to precise probability distributions which encode complete order relations over Ω, interval-based ones encode partial orders in the form ωi<IP ωj in case where ui<lj.

  • Major steps include NEPA process completion; start of final design; acquisition of a significant portion of the right-of-way; and, construction (including Federal approval of plans, specifications and estimates).

Related to NEPA process completion

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.

  • project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;

  • Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

  • Construction Completion Date means the Completion Date of the Construction as specified in the Statutory Declaration of Completion for the Project;

  • Construction Completion means physical construction of a cleanup action component is complete.

  • Notice to Proceed (NTP) means the authorization issued by the CO to start performance on this Contract.

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • Mechanical Completion means that (a) all components and systems of the Project have been properly constructed, installed and functionally tested according to EPC Contract requirements in a safe and prudent manner that does not void any equipment or system warranties or violate any permits, approvals or Laws; (b) the Project is ready for testing and commissioning, as applicable; (c) Seller has provided written acceptance to the EPC Contractor of mechanical completion as that term is specifically defined in the EPC Contract.

  • Commissioning test means tests applied to a distributed generation facility by the applicant after construction is completed to verify that the facility does not create adverse system impacts and performs to the submitted specifications. At a minimum, the scope of the commissioning tests performed shall include the commissioning test specified in Institute of Electrical and Electronics Engineers, Inc. (IEEE) Standard 1547 Section 5.4 "Commissioning tests".

  • Study Completion means the database for the Study has been locked and all Essential Documents have been provided to the Sponsor, including a copy of the letter from the Reviewing HREC acknowledging receipt of the final report and/or closure letter from the Principal Investigator.

  • Substantial Completion Date means the date on which Substantial Completion occurs.

  • Completion Period means the period starting from the date of issue of "Order" and required to complete the work in all respect.

  • Final Completion Date means the date on which Final Completion occurs.

  • Tests after Completion means the tests (if any) which are specified in the Contract and which are carried out in accordance with the Specification after the Works or a Section (as the case may be) are taken over by the Procuring Entity.

  • Commissioning Tests means all of the procedures and tests which, in accordance with the Reasonable and Prudent Standard, and in compliance with industry guidelines, practices and standards, are:

  • Testson Completion means the tests which are specified in the Contractor agreed by both Parties or instructed as a Variation, and which are carried out under Clause 9 [Tests on Completion] before the Works or a Section (as the case may be) are taken over by the Procuring Entity.

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • Tests on Completion means the tests which are specified in the Contract or agreed by both Parties or instructed as a Variation, and which are carried out under Clause 9 [Tests on Completion] before the Works or a Section (as the case may be) are taken over by the Procuring Entity.

  • Notice to Proceed means notice issued by the OPWC pursuant to Section IV of this Agreement. "OPWC" means the Ohio Public Works Commission created pursuant to Revised Code Section 164.02.

  • Improvement completion assurance means a surety bond, letter of credit,

  • Operational Acceptance Tests means the tests specified in the Technical Requirements and Agreed Project Plan to be carried out to ascertain whether the System, or a specified Sub system, is able to attain the functional and performance requirements specified in the Technical Requirements and Agreed Project Plan, in accordance with the provisions of GCC Clause 27.2 (Operational Acceptance Test).

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Target Completion Date has the meaning given such term in Section 3.3(b).

  • Generation Interconnection Feasibility Study means a study conducted by the Transmission Provider (in coordination with the affected Transmission Owner(s)) in accordance with Tariff, Part IV, section 36.

  • Phase 2 means the phase of the ATP comprised of: (1) improvements to the State Street Substation to receive Rebuilt Line 972; (2) the rebuilding of NYSEG’s existing Line 972 not performed in Phase 1; (3) construction of Relocated Line 15; (4) the construction of Bused Line 5; (5) improvements to the Elbridge Substation to receive Relocated Line 15; and (6) improvements to the Elbridge Substation to receive Bused Line 5.