Examples of Payment and Milestone Schedule in a sentence
The Down Payment specified in the Payment and Milestone Schedule provided in Appendix 3 shall be due upon receipt of the corresponding invoice from SpaceX following execution of this Agreement and will be paid in accordance with Section 5.2 herein.
Contractor shall promptly review the Scope Change Order Request and notify Owner in writing of the options for implementing the proposed Scope Change (including, if possible, any option that does not involve an extension of time) and the effect, if any, each such option would have on the Contract Price, the Guaranteed Completion Dates, the Construction Progress Milestone Dates, the Payment and Milestone Schedule, the Project Schedule and the Performance Guarantees.
The Contract Price shall be paid by Customer to SpaceX in accordance with the payment plan set forth in the Payment and Milestone Schedule, including the Down Payment and Milestone Payments, the former to be invoiced pursuant to Section 5.1.1 and the latter to be invoiced pursuant to Section 5.2 below.
For the Down Payment and each Milestone Payment, SpaceX shall submit to Customer an invoice for payment after completion of a Milestone consistent with the SOW, on or after the corresponding Milestone Payment due date listed in the Payment and Milestone Schedule, including SpaceX’s certification that the applicable Milestone completion criteria have been met in accordance with the Milestone completion criteria in the SOW.
Owner and Contractor may agree from time to time to amend the Payment and Milestone Schedule to reflect changes in the order of performance of the Services.
In the event and to the extent that any Force Majeure Events affect Contractor's ability to meet the Guaranteed Completion Dates, or the Construction Progress Milestone Dates, an equitable adjustment in one or more of such dates, the Payment and Milestone Schedule and the Project Schedule shall be made by agreement of Owner and Contractor or otherwise pursuant to Article 21 hereof.
Contractor acknowledges and agrees that any difficulty or extra cost it may encounter in performing the Services in compliance with such documentation will not entitle Contractor to any increase or adjustment in the Contract Price, the Guaranteed Completion Dates, the Construction Progress Milestone Dates, the Payment and Milestone Schedule, the Project Schedule, the Performance Guarantees or any other provision which may be affected thereby.
In the event of such a suspension by Contractor pursuant to clause (a) above, an equitable adjustment to one or more of the Contract Price, the Guaranteed Completion Dates, the Construction Progress Milestone Dates, the Payment and Milestone Schedule and the Project Schedule, and, as appropriate, such other provisions of this Agreement that may be affected thereby, shall be made by agreement between Owner and Contractor or otherwise pursuant to Article 12 or 21 hereof.
In the event Owner makes any such election(s), (i) the Contract Price shall be adjusted in accordance with the respective provisions of Section B of Appendix O hereto that are expressly set forth therein as being applicable to such scope option(s), and (ii) corresponding adjustments to the Payment and Milestone Schedule shall be made as reasonably agreed upon by Owner and Contractor.
Owner, without invalidating this Agreement, may order Scope Changes to the Services, in which event one or more of the Contract Price, the Construction Progress Milestone Dates, the Guaranteed Completion Dates, the Payment and Milestone Schedule, the Project Schedule and the Performance Guarantees shall be adjusted accordingly, if necessary.