Examples of Progress Milestone in a sentence
The Project Schedule shall indicate a Progress Milestone for completion of the Baseline Test that is not more than 180 days after NTP.
If, at any time, TSP’s actual progress in performing the Work as measured against the Project Schedule or any of the Progress Milestone Dates is inadequate to meet the requirements of this Contract, the Joint Board may so notify TSP.
The primary purpose of the progress meetings shall be to review the Project Schedule, the Progress Milestone Dates, and the Project Management Reports submitted by TSP and to examine and assess the actual progress of the Work, including the status of pending Change Orders and any other design or installation related issues which the parties may wish to discuss.
If TSP has reason to believe that the Work will not be performed consistent with the Progress Milestone Dates, TSP shall promptly so notify the Joint Board, specifying in its notice any corrective action planned by TSP.
The Project Schedule shall indicate a Progress Milestone for completion of the Pre- Production Controlled Test that is not more than 240 days after NTP.
The Pre-Toll Operations Readiness Deadline, the Mobilization Readiness Deadline, the East-End Bridge Tolling Readiness Deadline, the Downtown Bridges Temporary Traffic Configuration Tolling Readiness Deadline and the Downtown Bridges Final Traffic Configuration Tolling Readiness Deadline, and the other Progress Milestone Dates shall not be modified except by Change Order.
However, payment for the final Progress Milestone by City will not constitute a waiver, release or discharge of any claims or demands which City then has, or can subsequently acquire, against Contractor, its successors and assigns, for or on account of any matter or thing arising out of, or in any manner connected with, the performance of this Agreement.
TSP may be entitled to an extension of Progress Milestone Dates or Completion Deadlines, but no additional compensation due to delays in the TSP’s ability to progress the work caused solely by the deficiencies in the ETC Contractor’s work, provided all other conditions to a Change Order specified in Section 13 are satisfied.
The Project Schedule shall indicate a Progress Milestone for completion of the BOS Production Readiness Test that is not more than 365 days after NTP.
Acceptance by Contractor of payment of the final Progress Milestone payment pursuant to Section 7.D will constitute a waiver, release and discharge of any and all claims and demands of any kind or character which Contractor then has, or can subsequently acquire against City, its successors and assigns, for or on account of any matter or thing arising out of, or in any manner connected with, the performance of this Agreement.