Examples of Successfully Run in a sentence
If the Project does not meet the Minimum Performance Test Requirements, Seller shall take corrective action and repeat the Performance Test until the Performance Test is Successfully Run and the Minimum Performance Test Requirements are met.
In addition, if pursuant to Successfully Run XXXX Storage Capacity Tests, Seller achieves the Minimum XXXX Storage Capacity but fails to achieve the Guaranteed XXXX Storage Capacity, subject to any retest procedures and other remedies set forth in the Agreement, then Seller shall pay, as set forth in the Agreement, the Initial XXXX Storage Capacity Liquidated Damages, if any, and the Final XXXX Storage Capacity Liquidated Damages, if any.
In order to achieve Project Substantial Completion, pursuant to Section 12.7(h) of the Agreement the XXXX Storage Capacity as determined by a Successfully Run XXXX Storage Capacity Test must equal or exceed the Minimum XXXX Storage Capacity.
In order to achieve Project Substantial Completion, pursuant to Section 12.7(h) of the Agreement the Performance Tests as determined by a Successfully Run Performance Test must equal or exceed the Minimum Performance Tests Requirements.
In addition, if pursuant to Successfully Run PV Plant Capacity Tests, Seller achieves the Minimum PV Plant Capacity but fails to achieve the Guaranteed PV Plant Capacity, subject to any retest procedures and other remedies set forth in the Agreement, then Seller shall pay, as set forth in the Agreement, the Initial PV Plant Capacity Liquidated Damages, if any, and the Final PV Plant Capacity Liquidated Damages, if any.
With respect to each Performance Test, if Seller achieves the Minimum Performance Test Requirements pursuant to such Successfully Run Performance Test but cannot achieve the Minimum Guaranteed Plant Capacity, in the case of a Plant Capacity Test, or the Minimum Guaranteed Plant Reliability, in the case of a Plant Reliability Test , Seller shall pay to Purchaser the related liquidated damages as and when required under Article 15.
With respect to each Performance Test, if Seller achieves the Minimum Performance Test Requirements pursuant to such Successfully Run Performance Test but cannot achieve the Guaranteed XXXX XX Efficiency, in the case of a XXXX XX Efficiency Test, the Guaranteed XXXX Storage Capacity, in the case of a XXXX Storage Capacity Test, the Guaranteed PV Plant Capacity, in the case of a PV Plant Capacity Test, Seller shall pay to Purchaser the related liquidated damages as and when required under Article 15.
With respect to each Performance Test, if Seller achieves the Minimum Performance Test Requirements pursuant to such Successfully Run Performance Test but cannot achieve the Guaranteed PV Plant Capacity, in the case of a PV Plant Capacity Test, Seller shall pay to Purchaser the related liquidated damages as and when required under Article 15.
With respect to each Performance Test, if Seller achieves the Minimum Performance Test Requirements pursuant to such Successfully Run Performance Test but cannot achieve the Guaranteed XXXX XX Efficiency, in the case of a XXXX XX Efficiency Test, the Guaranteed XXXX Storage Capacity, in the case of a XXXX Storage Capacity Test, Seller shall pay to Purchaser the related liquidated damages as and when required under Article 15.
Contractor shall continue to perform curative work in accordance with this Section 9.10.5 until the Stage achieves the applicable Minimum Performance Standards and the applicable Performance Test is otherwise Successfully Run, notwithstanding the expiration of the Guaranteed Performance Levels Correction Period.