Actual Damages and Liquidated Damages Sample Clauses

Actual Damages and Liquidated Damages. DOM reserves the right to assess actual or liquidated damages upon the Contractor’s failure to provide timely services required pursuant to this Contract. Actual or liquidated damages for failure to meet specific performance standards as set forth in the Scope of Work may be assessed as specifically set forth in each performance standard. The Contractor shall be given fifteen (15) days notice to respond before DOM makes the assessment. Any assessment will be offset against the subsequent monthly payment(s) to the Contractor. If liquidated damages are known to be insufficient, then DOM has the right to pursue actual damages. Assessment of any actual or liquidated damages does not waive any other remedies available to DOM pursuant to this Contract or state or federal law. If the Contractor’s failure to perform satisfactorily exposes DOM to the likelihood of contracting with another person or entity to perform services required of the Contractor under this Contract, upon notice setting forth the services and penalty, DOM may withhold from the Contractor payments in an amount commensurate with the costs anticipated to be incurred. If costs are incurred, DOM shall account to the Contractor and return any excess to the Contractor. If the penalty is not sufficient, the Contractor shall immediately reimburse DOM the difference or DOM may offset from any payments due the Contractor. The Contractor will cooperate fully with the retained Contractor and provide any assistance it needs to implement the terms of its agreement for services for penalty. The following liquidated damages apply: Unauthorized utilization of the Data in violation of this Contract. $10,000 per occurrence. An occurrence means each unauthorized use, regardless of the number of beneficiaries or providers involved. Unauthorized use of DOM’s name, brand, or likeness in violation of this contract. $1,000 per occurrence. An occurrence means each unauthorized use. Failure to timely process claims per Centers for Medicare and Medicaid Services’ (CMS) requirements and additional criteria to be further defined during contract negotiations. $5,000 per occurrence per day. An occurrence means each request not completed timely (within ten (10) business days). Failure to meet the requirements of Health Insurance Portability and Accountability Act (HIPAA). $1,000 per occurrence. An occurrence means each improper use or disclosure of beneficiary information. Failure to meet reporting and deliverable requirements...
AutoNDA by SimpleDocs
Actual Damages and Liquidated Damages. The DFA reserves the right to assess actual or liquidated damages, upon Contractor’s failure to provide services in accordance with the requirements of the contract. The DFA may assess liquidated damages against the Contractor pursuant to this section, and deduct the amount of damages from the Contractor’s contingency payment. Any damages applied prior to recovery of money under this contract shall be applied against the first contingency payment. The DFA, at its sole discretion, may establish an installment deduction plan for the amount of any damages. The determination of the amount of damages shall be at the sole discretion of the DFA, within the ranges set forth below. Self-reporting by the Contractor shall be taken into consideration in determining the amount of damages to be assessed. Unless specified otherwise, the DFA shall give written notice to the Contractor of the failure that might result in the assessment of damages and the proposed amount of the damages. The Contractor shall have fifteen (15) calendar days from the date of the notice in which to dispute the DFA’s determination. The DFA may, at its sole discretion, assess damages between one dollar and zero cents ($1.00) and five thousand dollars and zero cents ($5,000.00) for each failure that occurs and/or remains uncorrected. Assessment of any actual or liquidated damages does not waive any other remedies available to the DFA pursuant to this Contract or state or federal law. If liquidated damages are known to be insufficient then the DFA has the right to pursue actual damages.

Related to Actual Damages and Liquidated Damages

  • Breach of Contract and Liquidated Damages A. Where OGS determines that the Contractor is not in compliance with the requirements of this Contract, and the Contractor refuses to comply with such requirements, or if it is found to have willfully and intentionally failed to comply with the MWBE participation goals set forth in the Contract, the Contractor shall be obligated to pay liquidated damages to OGS.

  • Withholding for unpaid wages and liquidated damages The FHWA or the contacting agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (2.) of this section.

  • Payment of Damages The indemnification required hereunder shall be made by periodic payments of the amount thereof during the course of the investigation or defense, within 10 days as and when reasonably specific bills are received or loss, liability, claim, damage or expense is incurred and reasonable evidence thereof is delivered. In calculating any amount to be paid by an indemnifying party by reason of the provisions of this Agreement, the amount shall be reduced by all reimbursements (including, without limitation, insurance proceeds) credited to or received by the other party related to the Damages.

  • Actual Damages Contractor is liable to CMHA for all actual and direct damages caused by Contractor’s default. In the event Contractor fails to provide services or material as provided for in the Contract Documents, CMHA may substitute the services and/or material from a third party. CMHA may recover the costs associated with acquiring substitute services and/or materials, less any expense or costs saved by Contractor’s default, from Contractor.

  • CONTRACT TIME AND LIQUIDATED DAMAGES (7-1-95) (Rev. 12-18-07) 108 SP1 G10 A The date of availability for this contract is September 26, 2016. The completion date for this contract is October 31, 2017. Except where otherwise provided by the contract, observation periods required by the contract will not be a part of the work to be completed by the completion date and/or intermediate contract times stated in the contract. The acceptable completion of the observation periods that extend beyond the final completion date shall be a part of the work covered by the performance and payment bonds. The liquidated damages for this contract are Two Thousand Dollars ($ 2,000.00) per calendar day.

  • Remedy Damages The Contractor shall promptly remedy damages and loss to property at the Site caused by the Contractor, by any Subcontractor, by anyone directly or indirectly employed by the Contractor or any such Subcontractor, or by anyone for whose acts the Contractor or any such Subcontractor may be liable. Should the Contractor cause damage to any Separate Contractor‘s work, the Contractor agrees, upon due notice, to settle with the Separate Contractor.

  • Compensation for Damages and Losses Investors of either Contracting Party whose investments suffer losses in the territory of the other Contracting Party owing to war or other armed conflict, revolution, a state of national emergency or revolt, shall be accorded treatment by such other Contracting Party not less favourable than that which the latter Contracting Party accords to its own investors or to investors of any third State as regards restitution, indemnification, compensation or other valuable consideration.

  • Deduction of Damages from Contract Price Upon prior written notice being issued to the Contractor, CMHA may deduct all or any part of the damages resulting from Contractor’s default from any part of the price still due on this Agreement.

  • Liquidated Damages for Delay In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of $500.00 per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this $500.00 per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the is $500.00 per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.

  • Consequential Damages Waiver NEITHER PARTY SHALL HAVE ANY LIABILITY ARISING OUT OF OR RELATED TO THIS AGREEMENT FOR ANY LOSS OF USE, LOST DATA, LOST PROFITS, FAILURE OF SECURITY MECHANISMS, INTERRUPTION OF BUSINESS, LOSS CAUSED BY THE INTERRUPTION, TERMINATION OR DELAYED OPERATION OF THE INTERNET, THIRD-PARTY TELECOMMUNICATION SERVICES OR THIRD-PARTY SECURITY FEATURES OR SYSTEMS, EXCEPT AS REQUIRED BY LAW. EXCEPT FOR CUSTOMER’S BREACH OF SECTION 1.4 (USE RESTRICTIONS) OR EITHER PARTY’S UNLAWFUL OR WILLFUL MISCONDUCT OR GROSS NEGLIGENCE, NEITHER PARTY SHALL BE LIABLE FOR ANY INDIRECT, SPECIAL, INCIDENTAL, EXEMPLARY, PUNITIVE, RELIANCE, OR CONSEQUENTIAL DAMAGES OF ANY KIND, EVEN IF INFORMED OF THE POSSIBILITY IN ADVANCE, SUFFERED BY ANY PARTY OR ANY PARTY CLAIMING ON BEHALF OF OR THROUGH THE OTHER PARTY, OR ANY OTHER THIRD PARTY RESULTING FROM OR ARISING OUT OF OR RELATED TO THIS AGREEMENT OR THE PERFORMANCE OR BREACH THEREOF.