Common use of Check Meters Clause in Contracts

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the Participating

Appears in 11 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISOISO-polled meters or the Participating TODistribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIAGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingDistribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by

Appears in 7 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISOISO-polled meters or the Participating TODistribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the Participatingof

Appears in 4 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement (Gia)

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s Transmission Provider's meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIAGIA, except as provided in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingArticle

Appears in 4 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the Participatingof

Appears in 3 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or Metering Equipment owned by the Participating TO’s metersMetering Party. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the Participatingof

Appears in 3 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the Participatingbe

Appears in 3 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or Metering Equipment owned by the Participating TO’s metersMetering Party. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIAGIA, except as provided in the case that no other means are available on a temporary basis Article 7.4 below. The check meters shall be subject at the option of the CAISO or the Participatingall reasonable times to inspection and examination by

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s Transmission Provider's meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except as provided in the case that no other means are available on a temporary basis Article 7.4 below. The check meters shall be subject at the option of the CAISO all reasonable times to inspection and examination by Transmission Provider or the Participatingits

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement (Lgia)

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the Participatingtemporary

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingParticipating TO. The check meters shall

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (Lgia)

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or Metering Equipment owned by the Participating TO’s metersMetering Party. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIAGIA, except as provided in the case that no other means are available on a temporary basis Article 7.4 below. The check meters shall be subject at the option of the CAISO all reasonable times to inspection and examination by Transmission Provider, Transmission Owner or the Participatingtheir designees. The

Appears in 1 contract

Samples: Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISOCAISOISO-polled meters or the Participating TOTO’sDistribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIALGIAGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingParticipating TO.

Appears in 1 contract

Samples: Generator Interconnection Agreement (Gia)

AutoNDA by SimpleDocs

Check Meters. The The. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISOCAISOISO-polled meters or the Participating TOTO’sDistribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingParticipating TO.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement (Lgia)

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters Transmission Owners’ meter(s) or the Participating TO’s CAISO polled meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIAAgreement, except as provided in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingArticle 7.4

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the a Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s metersMetering Equipment owned by a Metering Party. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except as provided in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingArticle 7.4

Appears in 1 contract

Samples: Asset Sale Agreement (CMS Energy Corp)

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s Transmission Provider's meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIATransitional Cluster GIA, except as provided in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingArticle 7.4

Appears in 1 contract

Samples: Transitional Cluster Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or Metering Equipment owned by the Participating TO’s metersMetering Party. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIAGIA, except as provided in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingArticle 7.4

Appears in 1 contract

Samples: Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TODistribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIAAgreement, except as provided in the case that no other means are available on a temporary basis at the option of the CAISO or the ParticipatingArticle 2.5.4

Appears in 1 contract

Samples: Standard Small Generator Interconnection and Operating Agreement (Ssgia)

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Interconnecting Participating TO’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the Participatingavailable

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Check Meters. The Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the CAISO-polled meters or the Participating TO’s Transmission Provider's meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LGIA, except in the case that no other means are available on a temporary basis at the option of the CAISO or the Participatingof

Appears in 1 contract

Samples: Generator Interconnection Agreement