Common use of Check Meters Clause in Contracts

Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the ISO-polled meters or Distribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this GIA, except in the case that no other means are available on a temporary basis at the option of the Distribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by Distribution Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.

Appears in 15 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)

AutoNDA by SimpleDocs

Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the ISO-polled meters or Distribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this GIALGIA, except in the case that no other means are available on a temporary basis at the option of the Distribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by Distribution Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.

Appears in 4 contracts

Samples: Service Agreement for Wholesale Distribution Service, Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement (Lgia)

Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the ISOCAISO-polled meters or Distribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this GIA, except in the case that no other means are available on a temporary basis at the option of the Distribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by Distribution Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Check Meters. The Interconnection CustomerCustomers, at its their option and expense, may install and operate, on its premises and on its their side of the ofthe Point of Interconnection, one or more check meters to check the ISO-polled meters or Distribution Provider’s metersinstalled by the STS Operating Agent. Such check meters shall be for check purposes only and shall not be used for the measurement of Instantaneous bi-directional analog real power and reactive power flows for purposes of this GIA, IA except as provided in the case that no other means are available on a temporary basis at the option of the Distribution ProviderArticle 11.4 below. The check meters shall be subject subject, at all reasonable times times, to inspection and examination by Distribution Provider the STS Operating Agent or its designee. The installation, operation and maintenance thereof shall be performed entirely by the Interconnection Customer Customers in accordance with Good Utility Practice.

Appears in 1 contract

Samples: Interconnection Agreement

Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the ISO-polled meters or Distribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this GIACLGIA, except in the case that no other means are available on a temporary basis at the option of the Distribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by Distribution Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.

Appears in 1 contract

Samples: Clustering Large Generator Interconnection Agreement (Clgia)

Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the ISO-polled meters or Distribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this GIA, except in the case that no other means are available on a temporary basis at the option of the Distribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by Distribution Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.thereof

Appears in 1 contract

Samples: Generator Interconnection Agreement

AutoNDA by SimpleDocs

Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the ISOCAISO-polled meters or Distribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this GIA, except in the case that no other means are available on a temporary basis at the option of the Distribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by Distribution Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.Practice.‌

Appears in 1 contract

Samples: Generator Interconnection Agreement

Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the ISO-polled meters or Distribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this GIACLGIA, except in the case that no other means are available on a temporary basis at the option of the Distribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by Distribution Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.Practice.‌

Appears in 1 contract

Samples: Clustering Large Generator Interconnection Agreement and Distribution Service Agreement

Check Meters. Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the ISO-polled meters or Distribution Provider’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this GIAGIACLGIA, except in the case that no other means are available on a temporary basis at the option of the Distribution Provider. The check meters shall be subject at all reasonable times to inspection and examination by Distribution Provider or its designee. The installation, operation and maintenance thereof shall be performed entirely by Interconnection Customer in accordance with Good Utility Practice.

Appears in 1 contract

Samples: Clustering Large Generator Interconnection Agreement (Giaclgia)