City Responsibility. 2.1 The CITY will furnish and pay for the actual cost of the materials, including any delivery or freight cost. The CITY will provide a purchase order and will be billed directly by the material supplier. The COUNTY may accumulate and xxxx the CITY for incidental material cost. 2.2 The CITY will pay for one-half of the COUNTY’s fuel used to construct this Project. The COUNTY will invoice the CITY for the fuel consumed at the conclusion of the Project. 2.3 The CITY will be responsible for all traffic control necessary to safely construct this project. This responsibility includes all advance notices, signage, barricades, pilot vehicles, and flagmen necessary to control traffic in and around the construction site. The CITY will be responsible for and provide portable message boards to supplement traffic control as needed. 2.4 The CITY will make all necessary repairs and preparations to the existing roadway prior to the COUNTY starting work. 2.5 The CITY will adjust all utilities, manholes and valve boxes for this Project. 2.6 The CITY will provide the COUNTY with a hydrant meter and all the water necessary for construction of the Project at no cost to the COUNTY. 2.7 The CITY will provide or pay for any engineering, survey, and laboratory testing required for this Project. 2.8 The CITY will furnish a nearby site for dumping all spoils and waste materials generated during construction of this Project. 2.9 The CITY will provide the material to backfill the pavement edges for this project. 2.10 If required, the CITY will be responsible for the design and development of a Storm Water Pollution Prevention Plan (SWPPP). The CITY further agrees to pay for all cost (including sub-contractor materials, labor and equipment) associated with the implementation of the plan. The COUNTY will be responsible for maintenance of the plan during the duration of the Project. Documentation and record keeping of the SWPPP will be the responsibility of the CITY.
Appears in 4 contracts
Samples: Interlocal Agreement, Interlocal Agreement, Interlocal Agreement
City Responsibility. 2.1 The CITY will furnish and pay for the actual cost of the materials, including any delivery or freight cost. The CITY will provide a purchase order and will be billed directly by the material supplier. The COUNTY may accumulate and xxxx bill the CITY for incidental material cost.
2.2 The CITY will pay for one-half of the COUNTY’s fuel used to construct this Project. The COUNTY will invoice the CITY for the fuel consumed at the conclusion of the Project.
2.3 The CITY will be responsible for all traffic control necessary to safely construct this project. This responsibility includes all advance notices, signage, barricades, pilot vehicles, and flagmen necessary to control traffic in and around the construction site. The CITY will be responsible for and provide portable message boards to supplement traffic control as needed.
2.4 The CITY will make all necessary repairs and preparations to the existing roadway prior to the COUNTY starting work.
2.5 The CITY will adjust all utilities, manholes and valve boxes for this Project.
2.6 The CITY will provide the COUNTY with a hydrant meter and all the water necessary for construction of the Project at no cost to the COUNTY.
2.7 The CITY will provide or pay for any engineering, survey, and laboratory testing required for this Project.
2.8 The CITY will furnish a nearby site for dumping all spoils and waste materials generated during construction of this Project.
2.9 The CITY will provide the material to backfill the pavement edges for this project.
2.10 If required, the CITY will be responsible for the design and development of a Storm Water Pollution Prevention Plan (SWPPP). The CITY further agrees to pay for all cost (including sub-contractor materials, labor and equipment) associated with the implementation of the plan. The COUNTY will be responsible for maintenance of the plan during the duration of the Project. Documentation and record keeping of the SWPPP will be the responsibility of the CITY.
Appears in 1 contract
Samples: Interlocal Agreement
City Responsibility. With respect to each part of the Project:
2.1 The CITY will furnish and pay for the actual cost of the all materials, including any delivery or freight cost. The CITY will provide a purchase order and will be billed directly by trucking costs, for the material supplier. The COUNTY may accumulate and xxxx the CITY for incidental material costProject.
2.2 The CITY will furnish all rights-of-way and plan specifications. The CITY will also furnish all engineering drawings, if necessary, which will include required drainage grades and American with Disabilities Act approved entrances, if required. The CITY will pay for one-half of the COUNTY’s fuel used to construct this Project. The COUNTY will invoice the CITY drainage culverts, if needed, for the fuel consumed at the conclusion any part of the Project.
2.3 The CITY will be responsible for all furnish necessary traffic control necessary controls including Type A barricades to safely construct this project. This responsibility includes all advance notices, signage, barricades, pilot vehicles, and flagmen necessary redirect traffic flow to control traffic in and around alternate lanes during the construction site. The phase of the Project; and
2.4 CITY will be responsible for and provide portable message boards to supplement traffic control as needed.
2.4 The CITY will make all necessary repairs and preparations to the existing roadway prior to the COUNTY starting worktemporary driving lane markings.
2.5 The CITY will adjust all utilities, manholes and valve boxes for this Projectprovide a porta toilet.
2.6 The CITY will provide ensure that the Project is cleared of obstructions which could damage COUNTY equipment during construction; and
2.7 CITY will verify the location of all utility locations, mark those locations and then remove the utilities that will interfere with a hydrant meter and all the water necessary for construction progress of the Project at no cost to the COUNTY.
2.7 The CITY will provide or pay for any engineering, survey, and laboratory testing required for this Project.
2.8 The CITY will furnish a nearby site for dumping all spoils and waste in close proximity to the job site for materials generated during construction of this Project.
2.9 The CITY will provide the material to backfill the pavement edges for this project.
2.10 If a Storm Water Pollution Prevention Plan is required, the CITY will be responsible for the design design, development, implementation and development of a Storm Water Pollution Prevention Plan (SWPPP). The CITY further agrees to pay for all cost (including sub-contractor materials, labor and equipment) associated with the implementation maintenance of the planPlan for the duration of each part of the Project. The COUNTY will be inform the CITY if the Plan needs maintenance during construction.
3.0 The CITY is responsible for maintenance of the plan during scheduling and milling cost required for the duration of the Project. Documentation and record keeping of the SWPPP will be the responsibility of the CITYPROJECT.
Appears in 1 contract
Samples: Interlocal Agreement
City Responsibility. 2.1 The CITY will furnish and pay for the actual cost of the materials, including any delivery or freight cost. The CITY will provide a purchase order and will be billed directly by the material supplier. The COUNTY may accumulate and xxxx the CITY for incidental material cost.
2.2 The CITY will pay for one-half of the COUNTY’s fuel used to construct this Project. The COUNTY will invoice the CITY for the fuel consumed at the conclusion of the Project.
2.3 The CITY will be responsible for all traffic control necessary to safely construct this project. This responsibility includes all advance notices, signage, barricades, pilot vehicles, and flagmen necessary to control traffic in and around the construction site. The CITY will be responsible for and provide portable message boards to supplement traffic control as needed.
2.4 The CITY will make all necessary repairs and preparations to remove the existing surface and make any necessary roadway repairs prior to the COUNTY starting work.
2.5 The CITY will adjust all utilities, manholes and valve boxes for this Project.
2.6 The CITY will provide the COUNTY with a hydrant meter and all the water necessary for construction of the Project at no cost to the COUNTY.
2.7 The CITY will provide or pay for any engineering, survey, and laboratory testing required for this Project.
2.8 The CITY will furnish a nearby site for dumping all spoils and waste materials generated during construction of this Project.
2.9 The CITY will provide the material to backfill the pavement edges for this project.
2.10 If required, the CITY will be responsible for the design and development of a Storm Water Pollution Prevention Plan (SWPPP). The CITY further agrees to pay for all cost (including sub-contractor materials, labor and equipment) associated with the implementation of the plan. The COUNTY will be responsible for maintenance of the plan during the duration of the Project. Documentation and record keeping of the SWPPP will be the responsibility of the CITY.
Appears in 1 contract
Samples: Interlocal Agreement