Computation of Fixed Charge. (Not as the part of the Tariff as the rate quoted is Xxx Xxx)
11.4.1 Subject to the provisions of this Clause 11.4, the Base Fixed Charge, as corrected for variation in WPI Index in accordance with Clause 11.3 shall be the Fixed Charge payable for Availability in each month of the relevant Accounting Year.
11.4.2 The obligations of the Utility to pay Fixed Charges in any Accounting Year shall in no case exceed an amount equal to the Fixed Charge due and payable for and in respect of the Normative Availability of 85% (eighty five per cent) computed with reference to the Contracted Capacity (the “Capacity Charge”). Provided, however, that in the event of Despatch of the Power Station with reference to beyond such 85% (eighty five per cent), Incentive shall be payable in accordance with the provisions of Clause 11.6.1.
11.4.3 Pursuant to the provisions of Clause 11.4.4, the Supplier shall not, for and in respect of any day, be entitled to receive payment of Fixed Charge for Availability exceeding 85% (eighty five per cent) thereof and in the event it supplies electricity to the Utility in excess of such 85% (eighty five per cent), such excess supply shall be eligible only for payment of Variable Charge, save and except the payment of Incentive due under the provisions of Clause 11.4.2.
11.4.4 In the event that any shortfall in supply of electricity to the Utility occurs on account of deficiency in transmission between the Point of Grid Connection and Delivery Point, Availability shall be deemed to be reduced in accordance with the provisions of Clause 11.5.2 and the Non-Availability arising as a consequence thereof shall, for the purposes of payment of Fixed Charge, be deemed to be Availability to the extent of 50% (fifty per cent) of the Non-Availability hereunder. Provided, however, that the Supplier may, in its sole discretion, Despatch the Power Station to the extent of full or part Non-Availability hereunder for supply to other Buyers, and to the extent of full or part Non- Availability hereunder for supply to other Buyers, and to the extent of such Despatch, the Utility shall not be liable to payment of any Fixed Charge due and payable in accordance with the provisions of this Clause 11.4.4. For the avoidance of doubt, the Parties expressly agree that if such deficiency in transmission is caused by an action or omission attributable to the Supplier, it shall not be reckoned for the purposes of computing Availability hereunder. The Parties further agree ...
Computation of Fixed Charge. 11.3.1 The obligations of the Aggregator to pay Fixed Charges in any Accounting Year shall in no case exceed an amount equal to the Fixed Charge due and payable for and in respect of the Normative Availability of 85% (eighty five per cent) computed with reference to the Contracted Capacity (the “Capacity Charge”). Provided, however, that in the event of Despatch of the Power Station beyond such 85% (eighty five per cent), Incentive shall be payable in accordance with the provisions of Clause 11.5.1.
11.3.2 The Supplier shall not, for and in respect of any day, be entitled to receive payment of Fixed Charge for Availability exceeding 85% (eighty five per cent) thereof, and in the event it supplies electricity to the Aggregator in excess of such 85% (eighty five per cent), such excess supply shall be eligible only for payment of Variable Charge, save and except the payment of Incentive due under the provisions of Clause 11.3.1.
11.3.3 In the event that any shortfall in supply of electricity to the Aggregator occurs on account of deficiency in transmission between the Point of Grid Connection and Drawal Point, Availability shall be deemed to be reduced in accordance with the provisions of Clause 11.4.2 and the Aggregator shall not be liable for payment of any Fixed Charge for the Non-Availability arising as a consequence thereof.
Computation of Fixed Charge. 11.4.1 Deleted.