Construction Planning. How the planning is submitted is to be discussed with the managing official. The first planning is to be introduced within 7 calendar days following tender award notification and it is to be updated every month during construction. This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 8 contracts
Samples: Public Works Contract, Public Works Contract, Public Works Contract
Construction Planning. How the planning is submitted is to be discussed with the managing official. The first planning is to be introduced within 7 15 calendar days following tender award notification and it is to be updated every month during construction. This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 7 contracts
Samples: Public Works Contract, Public Works Contract, Public Works Contract
Construction Planning. How the planning is submitted is to be discussed with the managing official. The first planning is to be introduced within 7 14 calendar days following tender award notification and it is to be updated every month during construction. This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 3 contracts
Samples: Public Works Contract, Public Works Contract, Public Works Contract
Construction Planning. 165 How the planning is submitted is to be discussed with the managing official. §166 The first planning is to be introduced within 7 15 calendar days following tender award notification and it is to be updated every month during construction. §167 This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. §168 After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 2 contracts
Samples: Public Works Contract, Public Works Contract
Construction Planning. How the planning is submitted is to be discussed with the managing official. The first planning is to be introduced within 7 15 calendar days following tender award notification notification, and it is to be updated every month during construction. This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 1 contract
Samples: Public Works Contract
Construction Planning. 166 How the planning is submitted is to be discussed with the managing official. §167 The first planning is to be introduced within 7 15 calendar days following tender award notification and it is to be updated every month during construction. §168 This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. §169 After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 1 contract
Samples: Public Works Contract
Construction Planning. 132 How the planning is submitted is to be discussed with the managing official. §133 The first planning is to be introduced within 7 15 calendar days following tender award notification and it is to be updated every month during construction. §134 This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. §135 After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 1 contract
Samples: Public Works Contract
Construction Planning. 131 How the planning is submitted is to be discussed with the managing official. §132 The first planning is to be introduced within 7 calendar days following tender award notification and it is to be updated every month 15 days during construction. §133 This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. §134 After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 1 contract
Samples: Public Works Contract
Construction Planning. How the planning is submitted is to be discussed with the managing official. The first planning is to be introduced within 7 calendar days following tender award notification and it is to be updated every month 15 days during construction. This draft construction planning provides, in addition to deadlines for the ‘on-site’ works as such, the timing for the different preliminary achievements such as the establishment of documents prescribed by the technical provisions, implementation plans and detailed plans, calculation notes, selection of equipment and materials, including the approval of related documents, the supplies, workshop or factory work, preliminary tests and conformity tests, etc. After it has been studied and remarks have been made and following approval of the contracting authority, the planning becomes contractually binding.
Appears in 1 contract
Samples: Public Works Contract