Deduction for Uncorrected Work. If the Owner deems it inexpedient to correct deficiencies in the Work pursuant to Section 18.01 of this Contract, the Owner may deduct the reasonable cost of correcting the deficiencies, including any attorney’s fees and additional fees and expenses of the Engineer, from the payment then due or thereafter due to the Contractor, but the making of such a deduction shall in no way be deemed an election of remedies by the Owner.
Deduction for Uncorrected Work. If the Engineer deems it expedient to correct damaged work or work is not done in accordance with the Contract, an proportionate deduction from the Contract value shall be made.
Deduction for Uncorrected Work. If Owner reasonably and in good xxxxx xxxxx it inexpedient to correct deficiencies in the Work pursuant to Section 15.1, Owner may deduct the reasonable cost of doing so from the payment then due, any retainage held by Owner, or any payment thereafter due EPC Contractor, but the making of such a deduction shall in no way be deemed an election or limitation of remedies by Owner.
Deduction for Uncorrected Work. If the City deems it not expedient to require the Contractor to correct work not done in accordance with the Contract Documents, an equitable deduction from the Contract Price will be made by agreement between the Contractor and the City and subject to settlement, in case of dispute, as herein provided.
Deduction for Uncorrected Work. 35 Section 16.3. Correction of Work before Final Payment 35 Article 17 INSURANCE 36
Deduction for Uncorrected Work. If Xxxx County deems it not expedient to require the Contractor to correct work not done in accordance with the Contract Documents, an equitable deduction from the Contract Price will be made by agreement between the Contractor and Xxxx County and subject to settlement, in case of dispute, as herein provided.
Deduction for Uncorrected Work a. If the City of River Falls deems it not expedient to require the Contractor to correct work not done in accordance with the contract documents, an equitable deduction from the contract price will be made by agreement between the Contractor and the City of River Falls and subject to settlement, in case of dispute, as herein provided.
Deduction for Uncorrected Work. If the Owner and the Design Professional deem it inexpedient to require the Contractor to correct the Work injured or not done in accordance with the Contract Documents, an equitable deduction from the Contract Price shall be made.
Deduction for Uncorrected Work. If the Owner deems it not expedient to require the Contractor to correct work not done in accordance with the contract documents, an equitable deduction form the contract price will be made by agreement between the Contractor and the Owner and subject to settlement, in case of dispute, as herein provided.
Deduction for Uncorrected Work. If the County deems it not expedient to require the Contractor to correct work not done in accordance with the Contract Documents, an equitable deduction from the Contract Price will be made by agreement between the Contractor and the County and subject to settlement, in case of dispute, as herein provided.