Delay in Achieving Commercial Operation Date Sample Clauses

Delay in Achieving Commercial Operation Date. (a) If the RE Supplier fails to achieve the Commercial Operation Date by the Scheduled Commercial Operation Date or has reasonable grounds for concluding that it is unlikely to achieve that objective, then the RE Supplier shall promptly give the BL&P written notice of such failure or anticipated failure, expeditiously provide the BL&P with a written explanation of the reason for such failure or anticipated failure, and provide the BL&P with written weekly progress reports describing the actions taken to achieve the Commercial Operation Date and the estimated time frame for completion of such actions.
AutoNDA by SimpleDocs
Delay in Achieving Commercial Operation Date. If the Commercial Operation Date does not occur by the Longstop Date as extended from time to time in accordance with the Articles 4.4.1, 4.4.2, 5.8.3 and 13.7, NEPCO may terminate this Agreement, in which event the provisions of Article 14.1.1 shall apply.

Related to Delay in Achieving Commercial Operation Date

  • Commercial Operation Date (COD) Bus Terminal and Commercial Complex shall be deemed to be complete when the Completion Certificate or the Provisional Certificate, as the case may be, is issued under the provisions of Article 14, and accordingly the commercial operation date of the Project shall be the date on which such Completion Certificate or the Provisional Certificate is issued (the “COD”). The Bus Terminal and Commercial Complex shall enter into commercial service on COD whereupon the Concessionaire shall be entitled to demand and collect Fee in accordance with provisions of Article 27 and that the entry of Bus Terminal or part thereof into commercial service shall always be subject to compliance with the provisions of Clause 18.3 and Clause 26.2.

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Commercial Operation Date (COD 15.1.1 The Project shall be deemed to be complete when the Completion Certificate or the Provisional Certificate, as the case may be, is issued under the provisions of Article 14, and accordingly the commercial operation date of the Project shall be the date on which such Completion Certificate or the Provisional Certificate is issued (the “COD”). The Project shall enter into commercial service on COD whereupon the Concessionaire shall be entitled to demand and collect Annuity Payments in accordance with the provisions of this Agreement.

  • Failure to Achieve Commercial Operation If the Large Generating Facility fails to achieve Commercial Operation, but it or another generating facility is later constructed and makes use of the Network Upgrades, the Participating TO shall at that time reimburse Interconnection Customer for the amounts advanced for the Network Upgrades. Before any such reimbursement can occur, the Interconnection Customer, or the entity that ultimately constructs the generating facility, if different, is responsible for identifying and demonstrating to the Participating TO the appropriate entity to which reimbursement must be made in order to implement the intent of this reimbursement obligation.

  • Initial Operation The following requirements shall be satisfied prior to Initial Operation of the Customer Facility:

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.

  • Synchronisation Commissioning and Commercial Operation 8.1 The Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.

  • WORKING TEST PERIOD Section One. The Working Test Period shall be deemed an extension of the examination process. Therefore, a determination of unsatisfactory performance during a Working Test Period shall be tantamount to a failure of the competitive exam.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.