Common use of Delayed authorisation Clause in Contracts

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof all items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 6 contracts

Samples: www.rites.com, rites.com, And Construction Agreement

AutoNDA by SimpleDocs

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a beyonda period of 60 (sixty) days from the date of completionof completion of all safety/critical items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and & commissioning as specified in Schedule-G.

Appears in 4 contracts

Samples: And Construction Agreement, And Construction Agreement, And Construction Agreement

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof all items issue of punch listthe Provisional Certificate, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percentper cent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 4 contracts

Samples: Procurement and Construction Agreement, Procurement and Construction Agreement, Procurement and Construction Agreement

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completion of all items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Samples: www.rites.com

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completion of all safety/critical items of the punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Samples: www.nicdc.in

AutoNDA by SimpleDocs

Delayed authorisation. 12.6.1 In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completion of all safety / critical items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percentper cent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Samples: Epc Agreement

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completioion of all safety/critical items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Samples: Procurement and Construction Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!