DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 13 contracts
Samples: Energy Technical Services Contract, Microsoft Software & Services Large Account Reseller Contract, Fiber Optic Cable Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract prosecute the work continuously and diligently. No diligently and no charges or claims for damages shall be made by the Contractor it for any delays or hindrances, regardless hindrances from any cause whatsoever during the progress of cause, any portion of the work specified in the performance of services under this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to to, acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor Contractor in the performance of a contract Contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 10 contracts
Samples: Human Service Funding Agreement, Human Services Funding Agreement, Human Service Funding Agreement
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will may be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor Contractor in the performance of a contract with the StateState Contract, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or the delays of subcontractors a subcontractor or suppliers supplier arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors Contractor, subcontractor, or suppliers.
Appears in 8 contracts
Samples: Services Agreement, Standard Services Contract, Services Agreement
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will may be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor Contractor in the performance of a contract with the StateState contract, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or the delays of subcontractors a subcontractor or suppliers supplier arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors Contractor, subcontractor, or suppliers.
Appears in 8 contracts
Samples: Standard Services Contract, Standard Services Contract, Standard Services Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract Agreement continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor Contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 3 contracts
Samples: Inmate Dental Services Contract, Inmate Mental Health Care Services Contract, Inmate Medical Health Care and Utilization Services Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract agreement continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 3 contracts
Samples: License Agreement, Contract (Tactical Solution Partners, Inc.), Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services Services under this Contract. Time extensions will shall be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor Contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 2 contracts
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services Services under this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, embargoes or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 2 contracts
Samples: Forensic Toxicology Drug Testing Laboratory Contract, Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract prosecute the work continuously and diligently. No diligently and no charges or claims for damages shall be made by the Contractor it for any delays or hindrances, regardless hindrances from any cause whatsoever during the progress of cause, any portion of the work specified in the performance of services under this Contract. Time extensions will may be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to to, acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers contractors arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliersContractor Personnel.
Appears in 1 contract
Samples: Software as a Service Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will may be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor Contractor in the performance of a contract with the Statean AOC contract, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays the delay of subcontractors a subcontractor or suppliers supplier arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors subcontractor or supplierssupplier.
Appears in 1 contract
Samples: Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual Contractual capacity, acts of another contractor Contractor in the performance of a contract Contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 1 contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to shall perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will may be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including including, but not restricted to to, acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the Statean AOC contract, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays the delay of subcontractors a subcontractor or suppliers supplier arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the its subcontractors or suppliers.
Appears in 1 contract
Samples: Staff Augmentation & Professional Consulting Services Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will may be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the ContractorContractor including, including but not restricted to to, acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor Contractor in the performance of a contract with the Statean AOC contract, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays the delay of subcontractors a subcontractor or suppliers supplier arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors subcontractor or supplierssupplier.
Appears in 1 contract
Samples: Standard Contract Agreement
DELAYS AND EXTENSIONS OF TIME. β The Contractor agrees to perform this Contract prosecute the work continuously and diligently. No diligently and no charges or claims for damages shall be made by the Contractor it for any delays or hindrances, regardless hindrances from any cause whatsoever during the progress of cause, any portion of the work specified in the performance of services under this Contract. Time extensions will may be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to to, acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers contractors arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.Contractor Personnel.β
Appears in 1 contract
Samples: Software as a Service Contract
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract Agreement continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 1 contract
Samples: Contract