DELAYS AND EXTENSIONS OF TIME. 2.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or of a consultant or separate contractor employed by the Owner; or by changes ordered in the Work by the Owner; or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; or by delay authorized by the Owner pending mediation and binding dispute resolution or by other causes that the Owner determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner may determine.
Appears in 12 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
DELAYS AND EXTENSIONS OF TIME. 2.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner Manager or of a consultant or separate contractor employed by the OwnerManager; or by changes ordered in the Work by the OwnerManager; or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; or by delay authorized by the Owner Manager pending mediation and binding dispute resolution or by other causes that the Owner Manager determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner Manager may determine.
Appears in 3 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder