Common use of DELAYS AND EXTENSIONS OF TIME Clause in Contracts

DELAYS AND EXTENSIONS OF TIME. 18.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract. 18.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the County, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.

Appears in 5 contracts

Samples: Contract for Public Works Yard Pipe Replacement, Contract for Knife Box Road Pipe Replacement, Contract for Paving/Patching Services

AutoNDA by SimpleDocs

DELAYS AND EXTENSIONS OF TIME. 18.1 14.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract. 18.2 14.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the County, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.

Appears in 3 contracts

Samples: Contract for Multi Road Pipe Replacement, Time and Materials Contract, Contract for Double Hills Road Expansion Conduit Install, Fiber Optic Cable Pull and Splicing

DELAYS AND EXTENSIONS OF TIME. 18.1 19.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract. 18.2 19.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County State in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the CountyState, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.

Appears in 3 contracts

Samples: Sales Contract, Contract, Employee Assistance Program Contract

DELAYS AND EXTENSIONS OF TIME. 18.1 19.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this ContractPA. 18.2 19.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County State in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the CountyState, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.

Appears in 1 contract

Samples: Intent to Participate

AutoNDA by SimpleDocs

DELAYS AND EXTENSIONS OF TIME. 18.1 20.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract. 18.2 20.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County State in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the CountyState, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.

Appears in 1 contract

Samples: Self Funded Egovernment Services Contract