DELAYS AND EXTENSIONS OF TIME. 18.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract. 18.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the County, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 5 contracts
Samples: Contract for Public Works Yard Pipe Replacement, Contract for Knife Box Road Pipe Replacement, Contract for Paving/Patching Services
DELAYS AND EXTENSIONS OF TIME. 18.1 14.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract.
18.2 14.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the County, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 3 contracts
Samples: Contract for Multi Road Pipe Replacement, Time and Materials Contract, Contract for Double Hills Road Expansion Conduit Install, Fiber Optic Cable Pull and Splicing
DELAYS AND EXTENSIONS OF TIME. 18.1 19.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract.
18.2 19.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County State in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the CountyState, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 3 contracts
Samples: Sales Contract, Contract, Employee Assistance Program Contract
DELAYS AND EXTENSIONS OF TIME. 18.1 19.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this ContractPA.
18.2 19.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County State in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the CountyState, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 1 contract
Samples: Intent to Participate
DELAYS AND EXTENSIONS OF TIME. 18.1 20.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract.
18.2 20.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County State in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the CountyState, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
Appears in 1 contract