Environment Clearance Sample Clauses

Environment Clearance. The IPP shall be liable to obtain Environment clearance as required under the Environment (Protection) Act, 1986 and as per Environment Impact Assessment (EIA) Notification dated 14th Sept. 2006. This provision shall not be applicable if the project falls in exempt category of projects.
AutoNDA by SimpleDocs
Environment Clearance o Consent to Establish for 5x270 MW received from Maharashtra Pollution Control Board vide letter no. BO/XX (P&P)/EIC No. NK-5641-10/E/CC-249 dated 29.06.2010. o Environment CleaPraRncOe fGor R5xE27S0SMWRErePceOiveRd TfromUMPiniTstOry oMf EnAvirRonCmHent, &20Fo1res5ts (MoEF) vide letter no. J-13012/11/2008-IA.II (T) dated 28.7.2010. o Consent to Operate of 2 units (Unit#1&2) received from MPCB vide letter dt 18th July, 2013 COAL LINKAGE: o Ministry of Coal, Government of India has approved the Coal Linkage for the projects vide Standing Linkage Committee – Long Term meeting held on November 12, 2008. o The coal has been allotted from South Eastern Coalfields Limited (1.83 MTPA), Mahanadi Coalfields Ltd (1.83 MTPA) and Western Coalfields Limited (1.56 MTPA). XXX received from SECL, MCL and WCL on 7.9.2009, 11.6.2009 and 13.6.2009 respectively. o FSA signed with MCL for 1.4648 MTPA on 23.08.2013 and with SECL for 2.712 MTPA on 03.09.2013 (FSA with SECL is inclusive of the coal quantity transferred from WCL to SECL).
Environment Clearance. Environmental Clearance (EC) is not required for the Project Highway under Schedule 7(f) as per S.O. 2559 (E), MoEF Notification of 22nd August 2013 (as amendment of 14th September 2006) i.e., Expansion of National Highways greater than 100 km involving additional right of way or land acquisition greater than 40m on the existing alignments and 60m on re-alignment or bypasses.
Environment Clearance. EC was obtained by company for mines vide letter no.-J-11015/46/2015- IA.II(M) on dated 05-01-2017 for capacity of 5.00 MTPA limestone (ROM). Later on amended environmental clearance obtained vide letter no. IA-J- 11015/46/2015-IA.II(M) on dated 08-01-2018 for incorporate of crusher within lease. Company obtained CTE vide letter no. F(Mines)/Chittorgarh (Nimbahera)/ 1867(1)/2017-2018/544-549 dated 26.04.2018 and CTO vide letter no. F(Mines)/Chittorgarh (Nimbahera)/1867(1)/2017-2018/538-543 dated 26.04.2018 for the capacity of 5.00 MTPA limestone (ROM) from RSPCB. This Review of Mining Plan with PMCP is submitted under Rule 17 (2) of MCR, 2016 and Rule 23 of MCDR, 2017 respectively for a period from 01.10.2023 to 31.03.2028. Mining Plan /Scheme of Mining Mining plan with PMCP was approved vide letter no. 682 (23) (827)/2015-RCOM dated 29-07-2015 from RCOM, IBM, Udaipur and Modification in the approved Mining plan was approved vide letter no. 548(4)(3) (1799)/2019 RCOM AJM 1464 for period of year - 2020-21 to 2023-

Related to Environment Clearance

  • Environment Health and Safety 24.4.1. The Supplier and its staff (and/or any sub-supplier and/or subcontractor) shall comply with the laws and regulations in force related to protection of the environment, the health and safety instructions applicable to the Goods and Services performed pursuant to the Contract and especially, if appropriate, to the Goodsand Services performedon any Site by a third company.

  • Smoke Free Environment The Lessor shall make all parts of the leased premise smoke-free. "

  • SECURITY CLEARANCE REQUIREMENTS ‌ The OCO must tailor security requirements (both facility and employee), clauses, provisions, and other applicable terms and conditions specific to each task order’s solicitation and award. Only those Contractors that meet the required security clearance levels on individual task order solicitations are eligible to compete for such task orders. In general, all necessary facility and employee security clearances shall be at the expense of the Contractor. In some cases, Government offices that conduct background investigations do not have a means for accepting direct compensation from Contractors and instead charge customer agencies for the background investigations. In these cases, the Contractor shall be flexible in establishing ways of reimbursing the Government for these expenses. The individual task order should specify the terms and conditions for reimbursement, if any, for obtaining security clearances. The Contractor shall comply with all security requirements in task orders awarded under XXXXX.

  • Environmental Safety Upon encountering any previously unknown potentially hazardous material, or other materials potentially contaminated by hazardous material, Contractor shall immediately stop work activities impacted by the discovery, secure the affected area, and notify the ODR immediately.

  • Security Clearance 6.7.1 Where specified by the Authority or the Contract user, the Supplier shall be responsible for ensuring that all Staff are security cleared to the level required by the Security Requirements not less than 5 Working Days before such person begins to perform the Services. If the Authority is responsible for applying for security clearance for Staff pursuant to this Clause 6.7.1, the Supplier shall provide a completed security clearance application form for such members of Staff to the Authority not less than 30 days before such members of Staff begin to perform the Services.

  • Environmental Health and Safety i. Environment, Health and Safety Performance. Seller acknowledges and accepts full and sole responsibility to maintain an environment, health and safety management system ("EMS") appropriate for its business throughout the performance of this Contract. Buyer expects that Seller’s EMS shall promote health and safety, environmental stewardship, and pollution prevention by appropriate source reduction strategies. Seller shall convey the requirement of this clause to its suppliers. Seller shall not deliver goods that contain asbestos mineral fibers.

  • SITE CLEARANCE ETC Allow for clearing the area of the site to be built upon of all grass, weeds, shrubs, trees with trunks not exceeding 200mm girth, debris, etc., including grubbing up all roots, scoffling up as required and cart away all vegetation and debris. Quantity m2 200 Rate 2 Stripping average 300mm thick layer of topsoil and stockpiling on site. m2 200

  • Working Environment The Parties agree that a safe and clean working environment is essential in order to carry out work assignments in a satisfactory manner. It will be the Employer's responsibility to ensure that all working areas and Employer-owned vehicles are maintained in a safe and clean condition.

  • Contractor Security Clearance Customers may designate certain duties and/or positions as positions of “special trust” because they involve special trust responsibilities, are located in sensitive locations, or have key capabilities with access to sensitive or confidential information. The designation of a special trust position or duties is at the sole discretion of the Customer. Contractor or Contractor’s employees and Staff who, in the performance of this Contract, will be assigned to work in positions determined by the Customer to be positions of special trust, may be required to submit to background screening and be approved by the Customer to work on this Contract.

  • Environmental Permit the use, handling, generation, storage, treatment, Release or disposal of Hazardous Materials at any property owned or leased by it or any of its Subsidiaries, except in compliance in all material respects with Environmental Laws.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!