Initial Commissioning Sample Clauses

Initial Commissioning. If the Work does not fulfil the requirements set out in this Section 18.1(a), the Operator will continue to monitor the treatment of Contaminated Water and will cause Commissioning Reports to be issued by the Operator’s Consultant from time to time until such time as the Operator’s Consultant issues a Commissioning Report which confirms the facts required by Section 18.1(a).
AutoNDA by SimpleDocs

Related to Initial Commissioning

  • Commissioning Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least fifteen (15) days written notice to the SLDC / ALDC / DISCOM as the case may be, of the date on which it intends to synchronize the Power Project to the Grid System. 4.1.2 Subject to Article 4.1.1, the Power Project may be synchronized by the Power Producer to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 4.1.3 The synchronization equipment and all necessary arrangements / equipment including Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the Power Producer at its generation facility of the Power Project at its own cost. The Power Producer shall synchronize its system with the Grid System only after the approval of GETCO / SLDC / ALDC and GEDA. 4.1.4 The Power Producer shall immediately after each synchronization / tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 4.1.5 The Power Producer shall commission the Project within SCOD. 4.1.6 The Power Producer shall be required to obtain Developer and/ or Transfer Permission, Key Plan drawing etc, if required, from GEDA. In cases of conversion of land from Agricultural to Non-Agriculture, the commissioning shall be taken up by GEDA only upon submission of N.A. permission by the Power Producer. 4.1.7 The Power Producer shall be required to follow the Forecasting and Scheduling procedures as per the Regulations issued by Hon’ble GERC from time to time. It is to clarify that in terms of GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 the procedures for Forecasting, Scheduling & Deviation Settlment are applicable to all solar generators having combined installed capacity above 1 MW connected to the State Grid / Substation including those connected via pooling stations.

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Decommissioning (a) The Contractor shall submit to the Designated Authority, for its approval, pursuant to sub-paragraph 4.11(d)(v), a Decommissioning Plan for the Development Area and a schedule of provisions for the Decommissioning Costs Reserve. (b) The Decommissioning Plan shall be revised and resubmitted to the Designated Authority for its approval at such times as are reasonable having regard to the likelihood that the Decommissioning Plan (including cost estimates thereunder) may need to be revised. (c) The Contractor shall carry out the Decommissioning Plan substantially in accordance with its terms. (d) Estimates of the monies required for the funding of the Decommissioning Plan shall be charged as Recoverable Costs beginning in the Calendar Year following the Calendar Year in which Commercial Production first occurs. The amount charged in each Calendar Year shall be calculated as follows: (i) The total Decommissioning costs at the expected date of Decommissioning shall first be calculated. (ii) There shall be deducted from such total Decommissioning costs the additions made to the Decommissioning Costs Reserve made, and taken as Recoverable Costs, in all previous Calendar Years together with interest on such Recoverable Costs calculated to the approved date of Decommissioning at the actual or forecast rate of Uplift (whichever is applicable). (iii) The residual Decommissioning costs, resulting from the calculations under sub-paragraph 4.14(d)(i) and (ii), shall then be discounted to the Calendar Year in question at the forecast rate of Uplift for each Calendar Year remaining until the Calendar Year of Decommissioning. (iv) The discounted total of residual Decommissioning costs shall then be divided by the total number of Calendar Years remaining prior to the Calendar Year of Decommissioning itself, including the Calendar Year in question. (v) The resultant amount shall be the addition to the Decommissioning Costs Reserve for the Calendar Year in question. (vi) It is the intention of this provision that the total accumulated provision allowed, including interest calculated to the Calendar Year of Decommissioning at the rate of Uplift, will equal the total Decommissioning costs. (vii) If the amount in sub-paragraph 4.14(d)(v) is a negative amount, then such amount shall be treated as a reduction of Recoverable Costs for the Calendar Year in question.

  • Contract Closure Contracting Officer shall give appropriate written notice to Purchaser when Purchaser has complied with the terms of this contract. Purchaser shall be paid refunds due from Timber Sale Account un- der B4.24 and excess cooperative deposits under B4.218.

  • Project Closeout a. Participate in final inspection to prepare punch lists for project contractor to correct and/or to complete listed items. Verify that items on punch lists have been completed successfully assist COUNTY Project Manager or designee to determine completion date and coordinate project close out. a. Coordinate the preparation, acceptance and distribution of project closeout documents in accordance with COUNTY Project Manager or designee procedures to clients.

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.

  • Construction Phase Services 3.1.1 – Basic Construction Services

  • Project Completion Report At the completion of construction and once a Project is placed in service, the Subrecipient must submit a Project Completion Report that includes the total number of units built and leased, affordable units built and leased, DR-MHP units built and leased, an accomplishment narrative, and the tenants names, demographics and income for each DR-MHP unit.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!