INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES Sample Clauses
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (6-18-13) 108 SP1 G14 K The Contractor shall complete the work required of Map #41 and shall place and maintain traffic on same. The date of availability for this intermediate contract time is June 7, 2017. The completion date for this intermediate contract time is August 20, 2017. The liquidated damages are One Thousand Five Hundred Dollars ($1,500.00) per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (5-21-13) 108 SP1 G14 I The Contractor shall complete the work required of installing each new inductive loop after the removal of each existing loop by the milling, patching or resurfacing operations and shall place and maintain traffic on same. The date of availability for this intermediate contract time for each inductive loop installation will be the date when the Contractor elects to disturb the existing inductive loop. The completion date for this intermediate contract time for each inductive loop installation will be the date which is seven (7) consecutive calendar days after the date of availability. The liquidated damages are Five Hundred Dollars ($ 500.00) per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow three lanes of traffic on I-40/I-85 during the following time restrictions: The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. The liquidated damages are Two Thousand Five Hundred Dollars ($ 2,500.00) per fifteen (15) minute time period.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 A The Contractor shall complete the required work of installing, maintaining, and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow a lane of traffic on US 29 during the following time restrictions: In addition, the Contractor shall not close or narrow a lane of traffic on US 29, detain and/or alter the traffic flow on or during holidays, holiday weekends, special events, or any other time when traffic is unusually heavy, including the following schedules:
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 D The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for ramp closures and restoring traffic to the existing traffic pattern. The Contractor shall not close Any Ramps during the following time restrictions: The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for road closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the road closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. The liquidated damages are Five Hundred Dollars ($ 500.00) per fifteen (15) minute time period.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 B The Contractor shall not narrow or close a lane of traffic on I-40 and SR 1103 (Catawba Avenue/ Bat Cave Road), detain and /or alter the traffic flow on or during holiday weekends, special events, or any other time when traffic is unusually heavy, including the following schedules:
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (6-18-13) 108 SP1 G14 K The Contractor shall complete all work required on Maps #2, #3, #13, #14, #35, and #47 and shall place and maintain traffic on same. The date of availability for this intermediate contract time is either June 11, 2019 or June 11, 2020 at the election of the Contractor. The completion date for this intermediate contract time is the date which is sixty-six (66) consecutive calendar days after and including the date the Contractor elects to begin this work. The liquidated damages are One Thousand Dollars ($ 1,000.00) per calendar day. At the preconstruction conference the Contractor shall declare his expected date for beginning work. Should the Contractor desire to revise this date after the preconstruction conference, he shall notify the Engineer in writing at least thirty (30) days prior to the revised date.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) (Rev. 6-18-13) 108 SP1 G14 H The Contractor shall complete the work required of Phase I, Step #2 as shown on Sheet TMP-2 and shall place and maintain traffic on same. The date of availability for this intermediate contract time is the date the Contractor elects to begin the work.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (6-18-13) (Rev. 2-28-22) 108 SP1 G14 L The Contractor shall complete the work required of removing the temporary alignment for Culvert BP-024-2270, and shall place and maintain traffic on same. The date of availability for this intermediate contract time is the completion date for Intermediate Contract Time Number 2. The completion date for this intermediate contract time is June 1, 2023. The liquidated damages are Six Hundred Dollars ($ 600.00) per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C