Issue of Interim Payment Certificates. No amount will be certified or paid until the Employer has received and approved the Performance Security and the relevant Advance Payment Bonds required to be submitted by the Contractor in accordance with clause 4.2 [Performance Security and Advance Payment Bonds]. Thereafter, the Engineer shall, within 28 days after receiving a Statement and supporting documents, issue to the Employer an Interim Payment Certificate which shall state the amount which the Engineer determines to be due in accordance with the Contract, with supporting particulars. However, prior to issuing a Taking-Over Certificate for the Works, the Engineer shall not be bound to issue an Interim Payment Certificate in an amount which would (after any deductions) be less than the minimum amount of Interim Payment Certificates (if any) stated in the Appendix to Tender. In this event, the Engineer shall give notice to the Contractor accordingly. An Interim Payment Certificate shall not be withheld for any other reason, although:
(a) if anything supplied or work done by the Contractor is not in accordance with the Contract, the cost of rectification or replacement may be withheld until rectification or replacement has been completed; and/or
(b) if the Contractor was or is failing to perform any work or obligation in accordance with the Contract, and had been so notified by the Engineer, the value of this work or obligation may be withheld until the work or obligation has been performed. The Engineer may in any Payment Certificate make any correction or modification that should properly be made to any previous Payment Certificate. A Payment Certificate shall not be deemed to indicate the Engineer's acceptance, approval, consent or satisfaction.
Issue of Interim Payment Certificates. No amount will be certified or paid until the Employer has received and approved the Performance Security and the relevant Interim Bonds required to be submitted by the Contractor in accordance with clause 4.2 [
Issue of Interim Payment Certificates. Delete the words “supporting documents” in line 3 paragraph 1 and replace by “all supporting documents from the contractor,”
Issue of Interim Payment Certificates. In the 2nd line of the 1st paragraph replace “28” with “14” “No Interim Payment Certificate will be issued or paid unless the monthly progress reports in accordance with amended Sub-Clause 4.21 [Progress Reports] are not submitted. After the Engineer has certified the Interim Payment Certificate, the Contractor shall issue a tax invoice to accompany the certified Interim Payment Certificate.”
Issue of Interim Payment Certificates. The first paragraph of Sub-Clause 14.6 shall be deleted, and the following substituted: "The Contractor and the Engineer shall confer on or about the last working day of each month in order to discuss and (if possible) agree the amounts to which the Contractor is entitled. Thereafter, the Engineer shall, within 14 (fourteen) days after receiving a Statement and supporting documents, issue to the Employer an Interim Payment Certificate which shall state the amount which the Engineer fairly determines to be due, with supporting particulars."