ME Maintenance Outage Extension. An extension of a maintenance outage (MO) beyond its estimated completion date. This is typically used where the original scope of work requires more time to complete than originally scheduled. Do not use this where unexpected problems or delays render the unit out of service beyond the estimated end date of the MO. PO
Appears in 10 contracts
Samples: Energy Storage Agreement, Power Purchase Agreement, Power Purchase Agreement
ME Maintenance Outage Extension. An extension of a maintenance outage (MO) beyond its estimated completion date. This is typically used where the original scope of work requires more time to complete than originally scheduled. Do not use this where unexpected problems or delays render the unit out of service beyond the estimated end date of the MO. POPO Planned Outage β An outage that is scheduled well in advance and is of a predetermined duration, lasts for several weeks and occurs only once or twice a year. (Boiler overhauls, turbine overhauls or inspections are typical planned outages.)
Appears in 6 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
ME Maintenance Outage Extension. An extension of a maintenance outage (MO) beyond its estimated completion date. This is typically used where the original scope of work requires more time to complete than originally scheduled. Do not use this where unexpected problems or delays render the unit out of service beyond the estimated end date of the MO. POPO Planned Outage - An outage that is scheduled well in advance and is of a predetermined duration, lasts for several weeks and occurs only once or twice a year. (Boiler overhauls, turbine overhauls or inspections are typical planned outages.)
Appears in 2 contracts
Samples: Scheduling and Asset Optimization Services Agreement (MMC Energy, Inc.), Scheduling and Asset Optimization Services Agreement (MMC Energy, Inc.)
ME Maintenance Outage Extension. An extension of a maintenance outage (MO) beyond its estimated completion date. This is typically used where the original scope of work requires more time to complete than originally scheduled. Do not use this where unexpected problems or delays render the unit out of service beyond the estimated end date of the MO. POPO Planned Outage β An outage that is scheduled well in advance and is of a predetermined duration, lasts for several weeks and occurs only once or twice a year. (Boiler overhauls, Solar Array replacement or inspections are typical planned outages.) PE
Appears in 2 contracts
ME Maintenance Outage Extension. An extension of a maintenance outage (MO) beyond its estimated completion date. This is typically used where the original scope of work requires more time to complete than originally scheduled. Do not use this where unexpected problems or delays render the unit out of service beyond the estimated end date of the MO. PO.
Appears in 1 contract
Samples: Scheduling and Asset Optimization Services Agreement (MMC Energy, Inc.)