Procurement Schedule. CMR shall prepare, for A/E’s review and TFC’s review and acceptance, a procurement schedule for items that must be ordered in advance of commencement of construction. 6.2.3.1.1 CMR shall timely expedite and coordinate the ordering and delivery of products and materials that must be ordered in advance of construction. 6.2.3.1.2 Upon the earlier of the execution of a Work Package requiring any Construction Services, or TFC’s issuance of a Notice to Proceed with any Construction Services, CMR shall (i) assume full responsibility for all materials and equipment assigned to CMR by TFC for Project-related items purchased by TFC, and (ii) obtain and bind all insurance coverages, including builder’s risk insurance, as required by “Exhibit H”.
Appears in 2 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
Procurement Schedule. CMR shall prepare, for A/E’s review and TFC’s review and acceptance, a procurement schedule for items that must be ordered in advance of commencement of construction.
6.2.3.1.1 CMR shall timely expedite and coordinate the ordering and delivery of products and materials that must be ordered in advance of construction.
6.2.3.1.2 Upon the earlier of the execution of a Work Package GMP requiring any Construction Services, or TFC’s issuance of a Notice to Proceed with any Construction Services, CMR shall (i) assume full responsibility for all materials and equipment assigned to CMR by TFC for Project-related items purchased by TFC, and (ii) obtain and bind all insurance coverages, including builder’s risk insurance, as required by “Exhibit H”.
Appears in 1 contract
Procurement Schedule. CMR shall prepare, for A/E’s review and TFC’s review and acceptance, a procurement schedule for items that must be ordered in advance of commencement of construction.
6.2.3.1.1 . CMR shall timely expedite and coordinate the ordering and delivery of products and materials that must be ordered in advance of construction.
6.2.3.1.2 . Upon the earlier of the execution of a Work Package requiring any Construction Services, or TFC’s issuance of a Notice to Proceed with any Construction Services, CMR shall (i) assume full responsibility for all materials and equipment assigned to CMR by TFC for Project-related items purchased by TFC, and (ii) obtain and bind all insurance coverages, including builder’s risk insurance, as required by “Exhibit H”.
Appears in 1 contract
Procurement Schedule. CMR shall prepare, for A/E’s review review, PMP’s review, and TFC’s review and acceptance, a procurement schedule for items that must be ordered in advance of commencement of construction.
6.2.3.1.1 CMR shall timely expedite and coordinate the ordering and delivery of products and materials that must be ordered in advance of construction.
6.2.3.1.2 Upon the earlier of the execution of a Work Package requiring any Construction Services, or TFC’s issuance of a Notice to Proceed with any Construction Services, CMR shall (i) assume full responsibility for all materials and equipment assigned to CMR by TFC for Project-related items purchased by TFC, and (ii) obtain and bind all insurance coverages, including builder’s risk insurance, as required by “Exhibit H”.
Appears in 1 contract