H5 Disruption The Contractor shall take reasonable care to ensure that in the performance of its obligations under the Contract it does not disrupt the operations of the Authority, its employees or any other contractor employed by the Authority.
Market Disruption (a) If a Market Disruption Event occurs in relation to a Loan for any Interest Period, then the rate of interest on each Lender’s share of that Loan for the Interest Period shall be the percentage rate per annum which is the sum of: (i) the Margin; (ii) the rate notified to the Agent by that Lender as soon as practicable and in any event before interest is due to be paid in respect of that Interest Period, to be that which expresses as a percentage rate per annum the cost to that Lender of funding its participation in that Loan from whatever source it may reasonably select; and (iii) the Mandatory Cost, if any, applicable to that Lender’s participation in the Loan. (b) In this Agreement “Market Disruption Event” means:
Market Disruption Event Section 6.3(a) of the Equity Definitions is hereby replaced in its entirety by the following:
Project Changes 1.8.1. All changes shall be administered per the UGC. 1.8.2. Upon authorization by the Owner, the Owner or Architect/Engineer will prepare and issue all changes to the Contract affecting cost, scope and/or time as a formal Change Order to the Contract on the standard University of Texas MD Xxxxxxxx Cancer Center Change Order form. The Change Order may include separate change issues, identified as Change Proposals and field orders. 1.8.3. Upon authorization by the Owner, Change Proposals may be issued to the Architect/Engineer for pricing by the Contractor. Contractor shall submit pricing to the Owner within twenty-one (21) days and pricing shall be indicated on the standard Owner "Change in Work Cost Analysis" ("Cost Analysis") form provided in the Pre-Construction Conference Brochure. Contractor may not include a Change Proposal within a Change Order unless the Owner has accepted the Change Proposal. 1.8.3.1. The Contractor shall summarize all costs for each change at each level of subcontractor and supplier by preparing the "Cost Analysis" form, and shall provide each subcontractor's cost summary on separate "Cost Analysis" forms as backup. Additional support documentation from both the Contractor and Contractor’s subcontractors is encouraged, but such will not replace use of the standard form. 1.8.3.2. When the Contractor believes it is entitled to a time extension, Contractor shall so state as part of Contractor’s response to the Change Proposal, including a justifica- tion for a time extension. Owner may grant time extensions only if a Change Proposal affects the activities on the Longest Path of an Owner approved Work Progress Schedule; i.e., when the Work impacts the "Contract Substantial Completion Date". 1.8.3.3. If the Owner’s Project Manager and Contractor cannot mutually agree upon a fair and reasonable cost and time settlement, the Owner’s Project Manager may: 1) Reject the quotation and void the Change Proposal, 2) Issue instructions to the Contractor to proceed on a time and material basis for a price to be determined later not to exceed a fixed maximum dollar and time, or 3) Issue a Unilateral Change Order. 1.8.3.4. The Owner’s Construction Inspector and/or Owner’s Project Manager may issue field orders directly to the Contractor for minor changes to the Contract, which can be negotiated in the field. Pricing backup is at the discretion of the Owner’s Construction Inspector, but pricing backup is required for any field order, the pricing backup is to be outlined on the "Cost Analysis" form. When the Owner and Contractor have signed the field order, the Work is authorized and the field order may be included in the next Change Order. 1.8.4. Request for payment for Change Order work may be submitted only after the Change Order has been fully executed.
Additional Disruption Events Change in Law: Applicable; provided that Section 12.9(a)(ii) of the Equity Definitions is hereby amended by adding the words “(including, for the avoidance of doubt and without limitation, adoption or promulgation of new regulations authorized or mandated by existing statute)” after the word “regulation” in the second line thereof.
Disruption 41.1 The Contractor shall take reasonable care to ensure that in the performance of its obligations under the Framework Agreement it does not disrupt the operations of the Authority, its employees or any other Contractor employed by the Authority. 41.2 The Contractor shall immediately inform the Authority of any actual or potential industrial action, whether such action be by their own employees or others, which affects or might affect its ability at any time to perform its obligations under the Framework Agreement. 41.3 In the event of industrial action by the Staff, the Contractor shall seek Approval to its proposals to continue to perform its obligations under the Framework Agreement. 41.4 If the Contractor’s proposals referred to in clause 41.3 are considered insufficient or unacceptable by the Authority acting reasonably, then the Authority may by notice terminate the Framework Agreement with immediate effect.
Force Majeure Delays In any case where either party hereto is required to do any act (other than the payment of money), delays caused by or resulting from Acts of God or Nature, war, civil commotion, fire, flood or other casualty, labor difficulties, shortages of labor or materials or equipment, government regulations, delay by government or regulatory agencies with respect to approval or permit process, unusually severe weather, or other causes beyond such party’s reasonable control the time during which act shall be completed, shall be deemed to be extended by the period of such delay, whether such time be designated by a fixed date, a fixed time or “a reasonable time.”
Business Disruption; Condemnation There shall occur a cessation of a substantial part of the business of Borrowers and their Subsidiaries (taken as a whole) for a period which materially adversely affects the capacity of Borrowers and their Subsidiaries to continue their business on a profitable basis; or any Borrower, any of its Subsidiaries or any Guarantor shall suffer the loss or revocation of any material license or permit now held or hereafter acquired by such Borrower, such Subsidiary or such Guarantor which is necessary to the continued or lawful operation of a material portion of the business of Borrowers and their Subsidiaries (taken as a whole); or any Borrower, any of its Subsidiaries or any Guarantor shall be enjoined, restrained or in any way prevented by court, governmental or administrative order from conducting all or any material part of the business affairs of Borrowers and their Subsidiaries (taken as a whole); or any material lease or agreement pursuant to which any Borrower, any of its Subsidiaries or any Guarantor leases, uses or occupies any Property shall be canceled or terminated prior to the expiration of its stated term, except any such lease or agreement the cancellation or termination of which could not reasonably be expected to have a Material Adverse Effect; or any material portion of the Collateral shall be taken through condemnation or the value of such Property shall be materially impaired through condemnation, except for any such condemnation that would not reasonably be expected to have a Material Adverse Effect.
Notification of market disruption The Agent shall promptly notify the Borrowers and each of the Lenders stating the circumstances falling within Clause 5.7 which have caused its notice to be given.
Force Majeure Events a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following: i) acts of God; ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities; iii) acts of war (whether declared or undeclared), invasion or civil unrest; iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG or of any Law or any of their respective obligations under this Agreement); v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals; vi) earthquakes, explosions, accidents, landslides; fire; vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality; viii) chemical or radioactive contamination or ionizing radiation; or ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs; x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.