Rescheduling of Tests. If the Independent Engineer certifies to the Participating ULBs and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Rescheduling of Tests. 14.6.1 If the Independent Engineer Construction Supervisor certifies to the Participating ULBs ULB and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Rescheduling of Tests. β If the Independent Engineer certifies to the Participating ULBs and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Samples: Concession Agreement